# Risk category

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Group of similar risks](https://pmdecoder.com/en/concept/group-of-similar-risks/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/risk-category-pmi/

## Definition

In PMI terms, a risk category groups possible causes of risk. Risks are assigned to a category in order to recognize clusters, pool responsibilities and direct responses at common causes. Categories can be taken from the levels of the risk breakdown structure but can also be formed on other grounds, for example by affected work packages, project phases, organizational units or objectives such as schedule, cost and quality. The categories a project uses are usually defined in the risk management plan.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Risk category](https://pmdecoder.com/en/glossary/risk-category/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The term corresponds to the cross-framework concept of risk category. The risk breakdown structure is the hierarchical arrangement from whose levels categories are often derived; a category is a single element of such an arrangement. A category has nothing to do with rating by probability and impact.

## In practice

In a research project, an analysis of the risk register shows that eight of twenty high-rated risks belong to the category “suppliers”. Instead of eight separate actions, the team agrees with procurement on a joint supplier meeting and a second source for the critical components.

## Frequently asked questions

### How many risk categories make sense?

Enough for risks to be assigned unambiguously and for clusters to become visible. Categories that are too fine scatter the risks; categories that are too coarse hide patterns.

### Can a risk belong to several categories?

With a breakdown by cause, a single assignment is advisable. Other characteristics, such as phase or affected objective, can be recorded as an additional view.

## Related terms

- [Risk category](https://pmdecoder.com/en/glossary/risk-category/)
- [Risk breakdown structure](https://pmdecoder.com/en/glossary/risk-breakdown-structure-pmi/)
- [Risk register](https://pmdecoder.com/en/glossary/risk-register-pmi/)
- [Risk management plan](https://pmdecoder.com/en/glossary/risk-management-plan-pmi/)
- [Root cause analysis](https://pmdecoder.com/en/glossary/root-cause-analysis-pmi/)

---