# Risk breakdown structure

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Hierarchical breakdown of risk sources](https://pmdecoder.com/en/concept/hierarchical-breakdown-of-risk-sources/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/risk-breakdown-structure-pmi/

## Definition

The risk breakdown structure (RBS) arranges the possible sources of risk in a hierarchy. At the top level there are broad areas, such as technical, organizational, commercial and external sources; below they are refined step by step, for example into requirements, technology, suppliers, regulations or weather. PMI uses the RBS mainly as a framework for risk identification, so that no sources are overlooked, and as a basis for risk categories. It can be defined organization-wide and tailored for each project, and is often specified in the risk management plan.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Risk breakdown structure](https://pmdecoder.com/en/glossary/risk-breakdown-structure/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The term corresponds to the risk breakdown structure in ISO 21506. Unlike the work breakdown structure, the RBS does not break down work but cause areas. The risk register contains individual risks; the RBS provides the structure into which they can be slotted.

## In practice

A municipal administration is preparing to move into a new office building. The project manager uses the RBS provided by the project management office, with the main branches technology, organization, legal and environment, and adds “public participation” to the environment branch. In the risk workshop, the team goes through the branches one by one and assigns each risk it finds to a branch.

## Frequently asked questions

### Does every project need its own RBS?

Not necessarily. Many organizations provide a standard RBS. The project adopts it and tailors it to its particular circumstances.

### How does the RBS help with evaluation?

When risks are assigned to branches, it becomes visible where they cluster. This helps to tackle causes together instead of treating each risk separately.

## Related terms

- [Risk breakdown structure](https://pmdecoder.com/en/glossary/risk-breakdown-structure/)
- [Risk category](https://pmdecoder.com/en/glossary/risk-category-pmi/)
- [Risk identification](https://pmdecoder.com/en/glossary/risk-identification-pmi/)
- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure-pmi/)
- [Risk management plan](https://pmdecoder.com/en/glossary/risk-management-plan-pmi/)

---