# Risk avoidance

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Eliminating a risk](https://pmdecoder.com/en/concept/eliminating-a-risk/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/risk-avoidance/

## Definition

With risk avoidance, the situation from which a risk arises is not entered into at all. This can mean replacing an unproven technology with a proven one, not engaging an unreliable supplier, dropping a particularly exposed part of the scope or scheduling work so that a hazard does not occur. The probability of the risk thus falls to zero.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Risk avoidance](https://pmdecoder.com/en/glossary/risk-avoidance-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Risk mitigation lowers probability or impact but leaves the risk in place; avoidance removes it. Risk transfer shifts the consequences to third parties. Avoidance often comes at a price: anyone who forgoes a new technology usually forgoes its advantages as well.

## In practice

An organizer is planning an open-air concert in October. The greatest threat is bad weather, which would lead to cancellation and refunds. Instead of an expensive roof structure, the organizer moves the event to an exhibition hall. The weather risk disappears completely, but the rental costs rise and the special atmosphere of an open-air event is lost. The organizer explicitly weighs up these disadvantages before deciding.

## Frequently asked questions

### Is avoidance always the best strategy?

No. It is safe, but it can be expensive or reduce the benefit of the project. Mitigation is often more economical.

### Which risks should be avoided?

Above all those with severe, unacceptable consequences, for example for safety, health or the survival of the company.

## Related terms

- [Risk response](https://pmdecoder.com/en/glossary/risk-response/)
- [Risk mitigation](https://pmdecoder.com/en/glossary/risk-mitigation/)
- [Risk transfer](https://pmdecoder.com/en/glossary/risk-transfer/)
- [Risk acceptance](https://pmdecoder.com/en/glossary/risk-acceptance/)

---