# Risk assurance

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.77
- Edition: ISO 21506:2024
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/risk-assurance/

## Definition

Risk assurance takes an outside look at how risks are being handled. It asks not only whether risks are recorded and treated but whether the organization can trust that the investment in the undertaking will still pay off. Typical activities are independent reviews of the risk register, stress tests of the schedule and cost plans, plausibility checks of the reserves and reports to the sponsor or governing body. It is carried out by people who are not themselves responsible for responding to the risks.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

Risk management identifies, assesses and treats risks within the project. Risk assurance checks whether this approach works and whether the statements about it can be relied on. It resembles project assurance but concentrates on risks and on whether the investment is sound. It differs from an internal audit in that it judges prospectively rather than checking compliance with rules after the event.

## In practice

A transport ministry is funding the upgrade of a railway line at a cost of 1.8 billion euros. Before releasing the next tranche, it commissions an independent team to carry out risk assurance. The team finds that the risk register looks complete, but the risk contingency reserve is based on prices from three years ago and permit risks for two bridges are missing. The ministry only releases the tranche after the project company has revised its cost forecast and increased the reserve.

## Frequently asked questions

### Who carries out risk assurance?

People or units that are independent of the project, such as a project management office, an internal review function or external experts. What matters is that they can judge without a conflict of interest.

### When is risk assurance worthwhile?

Above all before major investment decisions, such as releasing further budget tranches, and for large or novel undertakings where misjudgements would be expensive.

## Related terms

- [Project assurance](https://pmdecoder.com/en/glossary/project-assurance/)
- [Risk](https://pmdecoder.com/en/glossary/risk/)
- [Risk contingency reserve](https://pmdecoder.com/en/glossary/risk-contingency-reserve/)
- [Risk management](https://pmdecoder.com/en/glossary/risk-management/)
- [Business case](https://pmdecoder.com/en/glossary/business-case/)

---