# Risk analysis

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Examination of identified risks](https://pmdecoder.com/en/concept/examination-of-identified-risks/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/risk-analysis/

## Definition

Risk analysis follows risk identification and assesses how significant the risks found are. It clarifies causes and relationships, estimates probability and impact, and ranks the risks by priority. A distinction is made between qualitative analysis using levels and quantitative analysis using numerical values; often risks are first assessed qualitatively and only the most important ones are examined in more depth quantitatively.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Risk analysis](https://pmdecoder.com/en/glossary/risk-analysis-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Narrower terms: [Qualitative risk analysis](https://pmdecoder.com/en/glossary/qualitative-risk-analysis/), [Quantitative risk analysis](https://pmdecoder.com/en/glossary/quantitative-risk-analysis/)

## Distinction

Identification asks which risks exist, analysis how serious they are, and response what is done about them. In everyday language, risk analysis is often used for risk management as a whole. The risk assessment required by German occupational safety law (Gefährdungsbeurteilung) is a legally regulated special form with its own procedure.

## In practice

A project to relocate a data centre has identified 40 risks. In the qualitative analysis, eight fall into the red area, including failure of the cooling during the move. For these eight, the team prepares a quantitative analysis of the possible downtime and costs. The result justifies hiring a mobile cooling unit for the week of the move, at a cost well below the expected damage.

## Frequently asked questions

### Who carries out the risk analysis?

The project manager with the team and experts who can assess the particular risks, supported by risk managers in large projects.

### How often is the analysis carried out?

Comprehensively at the start of the project and regularly afterwards, so that new risks and changed assessments are taken into account.

## Related terms

- [Risk management](https://pmdecoder.com/en/glossary/risk-management/)
- [Risk identification](https://pmdecoder.com/en/glossary/risk-identification/)
- [Risk matrix](https://pmdecoder.com/en/glossary/risk-matrix/)
- [Risk response](https://pmdecoder.com/en/glossary/risk-response/)

---