# Risk analysis

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Examination of identified risks](https://pmdecoder.com/en/concept/examination-of-identified-risks/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/risk-analysis-pmi/

## Definition

In PMI terms, risk analysis is the work that lies between identifying risks and dealing with them. Identified risks are examined to determine how likely they are to occur, how strongly they would affect which objectives, and which other characteristics matter, such as urgency, proximity of possible occurrence or links to other risks. PMI distinguishes two forms: qualitative analysis, which prioritizes risks by means of ratings, and quantitative analysis, which numerically estimates the combined effect of risks on the overall result. The outcome forms the basis for choosing risk responses.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Risk analysis](https://pmdecoder.com/en/glossary/risk-analysis/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Risk management](https://pmdecoder.com/en/glossary/risk-management-pmi/)
- Narrower terms: [Qualitative risk analysis](https://pmdecoder.com/en/glossary/qualitative-risk-analysis-pmi/), [Quantitative risk analysis](https://pmdecoder.com/en/glossary/quantitative-risk-analysis-pmi/)

## Distinction

The term corresponds to the cross-framework concept of risk analysis. It is the umbrella term for qualitative risk analysis and quantitative risk analysis. It differs from risk identification in that the latter finds and describes risks; analysis evaluates them. Selecting actions already belongs to risk response.

## In practice

After a workshop, a construction project has 40 risks on record. The team rates each one using a probability and impact matrix. For the twelve highest-rated risks it also runs a simulation of their schedule impact to see how likely the planned handover date still is.

## Frequently asked questions

### Does every project need quantitative analysis?

No. Qualitative analysis is appropriate almost always. Quantitative analysis is mainly worthwhile for large, complex or strategically important projects and requires reliable data.

### How often is risk analysis performed?

Repeatedly throughout the life of the project. New risks emerge, and the assessment of known risks changes as more information becomes available.

## Related terms

- [Risk analysis](https://pmdecoder.com/en/glossary/risk-analysis/)
- [Qualitative risk analysis](https://pmdecoder.com/en/glossary/qualitative-risk-analysis-pmi/)
- [Quantitative risk analysis](https://pmdecoder.com/en/glossary/quantitative-risk-analysis-pmi/)
- [Probability and impact matrix](https://pmdecoder.com/en/glossary/probability-and-impact-matrix/)
- [Risk identification](https://pmdecoder.com/en/glossary/risk-identification-pmi/)
- [Expected monetary value](https://pmdecoder.com/en/glossary/expected-monetary-value-pmi/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.