# Responsibility assignment matrix

abbr. RAM

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.75
- Edition: ISO 21506:2024
- Concept: [Assigning responsibilities to tasks](https://pmdecoder.com/en/concept/assigning-responsibilities-to-tasks/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/responsibility-assignment-matrix/

## Definition

A responsibility assignment matrix lists tasks, work packages or deliverables in rows and roles or people in columns. The cells show which type of involvement applies in each case. The most widely used scheme is RACI: responsible for carrying out the work, accountable for final ownership, consulted for specialist input and informed for being kept up to date.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Responsibility assignment matrix](https://pmdecoder.com/en/glossary/responsibility-assignment-matrix-pmi/) | equivalent | — |
| PM² | [RASCI](https://pmdecoder.com/en/glossary/rasci/) | closely related | fixed form with the five roles responsible, accountable, supporting, consulted, informed |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Other terms

- RAM (abbreviation)
- RACI matrix (related, not equivalent)

## Distinction

The organization chart shows who reports to whom, the responsibility assignment matrix who does what. The work breakdown structure provides the rows, the roles from the organization chart the columns. Variants such as RASCI add further types of involvement, for example supporting roles.

## In practice

When a new HR information system is introduced, there is a dispute about who should clean up the master data. The project manager draws up a responsibility assignment matrix for the twenty most important results. It turns out that both the HR department and IT had entered an A for data cleansing. After half an hour of clarification, accountability lies with the HR department and IT is listed as supporting.

## Frequently asked questions

### How many accountable roles may there be per row?

Exactly one. If two roles are jointly accountable, in case of doubt neither feels responsible.

### How detailed should the matrix be?

As coarse as possible and as detailed as necessary. Detail pays off for interfaces and known points of conflict, but usually not for routine tasks.

## Related terms

- [Project role](https://pmdecoder.com/en/glossary/project-role/)
- [Organization chart](https://pmdecoder.com/en/glossary/organization-chart/)
- [Delegated authority](https://pmdecoder.com/en/glossary/delegated-authority/)
- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure/)
- [Work package](https://pmdecoder.com/en/glossary/work-package/)

---