# Responsibility assignment matrix

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Assigning responsibilities to tasks](https://pmdecoder.com/en/concept/assigning-responsibilities-to-tasks/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Canonical version: https://pmdecoder.com/en/glossary/responsibility-assignment-matrix-pmi/

## Definition

In PMI usage, the responsibility assignment matrix (RAM) is a grid that assigns project resources to work packages or tasks. The rows usually list elements of the work breakdown structure or individual activities, the columns people, roles or organizational units. The cells show who is involved and in what way. A RAM can link organizational units with work packages at a high level, or individual people with activities at a detailed level. The best-known form is the RACI chart with the roles responsible, accountable, consulted and informed.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Responsibility assignment matrix](https://pmdecoder.com/en/glossary/responsibility-assignment-matrix/) | equivalent | — |
| PM² | [RASCI](https://pmdecoder.com/en/glossary/rasci/) | closely related | fixed form with the five roles responsible, accountable, supporting, consulted, informed |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The RAM corresponds to the responsibility assignment matrix in the standard. The RASCI chart in PM² is a specific variant with an additional supporting role. The organizational breakdown structure supplies the organizational units, the work breakdown structure the work packages; the RAM brings both together in one table. An important rule with RACI is that only one person is accountable for each task.

## In practice

In a project to introduce a document management system, the project manager sets up a RAM. For the work package “Data migration”, the IT architect is accountable, two developers carry out the work, the data protection officer is consulted and the business units are informed. Going through the table reveals that nobody is accountable for training; this is resolved at the next team meeting.

## Frequently asked questions

### Is RACI the same as a responsibility assignment matrix?

RACI is a common form of RAM, but not the only one. Organizations also use other codes, for example with additional roles for support or sign-off, or simple crosses to indicate involvement.

### How detailed should a RAM be?

Detailed enough for everyone to recognize their tasks and for no gaps to remain. In large projects it is worth having a RAM per level: a high-level one for organizational units and a detailed one within sub-teams.

## Related terms

- [Responsibility assignment matrix](https://pmdecoder.com/en/glossary/responsibility-assignment-matrix/)
- [RASCI](https://pmdecoder.com/en/glossary/rasci/)
- [Work package](https://pmdecoder.com/en/glossary/work-package-pmi/)
- [Organizational breakdown structure](https://pmdecoder.com/en/glossary/organizational-breakdown-structure-pmi/)
- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure-pmi/)

---