# Resource planning

also: Capacity planning

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Determining resource needs and deployment](https://pmdecoder.com/en/concept/determining-resource-needs-and-deployment/)
- Topic area: [Resources and estimating](https://pmdecoder.com/en/area/resources-and-estimating/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/resource-planning/

## Definition

Resource planning derives the demand for staff, equipment and materials from activities, effort and dates. It defines which skills are needed, how many people are deployed at which times and which equipment or rooms have to be reserved. The demand is then compared with availability, and bottlenecks are resolved by rescheduling, buying in capacity or setting priorities.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Resource management plan](https://pmdecoder.com/en/glossary/resource-management-plan/) | partially overlapping | denotes the plan containing the rules for acquiring, deploying and releasing resources |

## Other terms

- Capacity planning (synonym)
- Resource management (related, not equivalent)

## Distinction

Resource planning determines demand and assignment; resource levelling then removes overloads. Staffing planning is the part of it that concerns people only. In multi-project management, resource planning is carried out across projects, because the same people work on several initiatives.

## In practice

An IT department with forty employees supports twelve projects at the same time. In the past, each project manager sent their demand to the team leads by e-mail; today everyone enters it by role and calendar week in a shared overview. The first comparison shows that the two database specialists are booked at 180 per cent in the autumn. The head of department postpones one project by six weeks and engages an external service provider for another.

## Frequently asked questions

### How far ahead should resources be planned?

Roughly for the entire project duration, and bindingly for the next weeks to months. For scarce specialists and hired equipment, a longer lead time pays off.

### What is a resource request?

The formal request for staff or equipment addressed to the responsible unit, such as line management or purchasing. It makes demands binding and traceable.

## Related terms

- [Resource](https://pmdecoder.com/en/glossary/resource/)
- [Resource levelling](https://pmdecoder.com/en/glossary/resource-levelling/)
- [Resource histogram](https://pmdecoder.com/en/glossary/resource-histogram/)
- [Resource breakdown structure](https://pmdecoder.com/en/glossary/resource-breakdown-structure/)
- [Project human resource management](https://pmdecoder.com/en/glossary/project-human-resource-management/)

---