# Resource loading

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.73
- Edition: ISO 21506:2024
- Topic area: [Resources and estimating](https://pmdecoder.com/en/area/resources-and-estimating/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/resource-loading/

## Definition

Resource loading determines, for each piece of planned work, which resources are needed, in what quantity and in which period, for example hours per qualification, machine time or quantities of material. It applies to projects just as much as to programmes, portfolios and related work. In practice, the requirements identified quickly run up against limits, such as the hours staff actually have available, what contracts with suppliers allow, or whether material can be delivered in time. These limits are therefore taken into account from the outset.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

Resource loading establishes what is needed. Resource planning assigns specific resources to these needs, and resource levelling resolves overloads. The resource breakdown structure provides the standard categories in which the needs are expressed.

## In practice

A software company is planning 14 work packages for a customer project. Resource loading shows the monthly need for development, testing and database support. In the third month, 2.5 full-time database specialists are needed, but the company has only one person with this qualification, who is also half committed to another project. The project manager postpones two work packages and brings in an external specialist for six weeks.

## Frequently asked questions

### Where does resource loading start?

With the work breakdown structure and the activities, because needs can only be determined for known work. Experience and the judgement of the people who will do the work are helpful.

### Do the needs have to be broken down over time?

Yes, at least roughly. A total requirement of 2,000 hours says little if it is unclear whether they will be needed over three months or twelve.

## Related terms

- [Resource planning](https://pmdecoder.com/en/glossary/resource-planning/)
- [Resource levelling](https://pmdecoder.com/en/glossary/resource-levelling/)
- [Resource breakdown structure](https://pmdecoder.com/en/glossary/resource-breakdown-structure/)
- [Basis of estimate](https://pmdecoder.com/en/glossary/basis-of-estimate/)
- [Resource histogram](https://pmdecoder.com/en/glossary/resource-histogram/)

---