# Resource levelling

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Adjusting the schedule to available capacity](https://pmdecoder.com/en/concept/adjusting-the-schedule-to-available-capacity/)
- Topic area: [Resources and estimating](https://pmdecoder.com/en/area/resources-and-estimating/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/resource-levelling/

## Definition

In resource levelling, activities are moved, split or reassigned until the load on every resource no longer exceeds its availability. If the available float is not sufficient for this, the project end date moves. A milder form, resource smoothing, only moves activities within their float and accepts that overloads may not disappear completely.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Resource leveling](https://pmdecoder.com/en/glossary/resource-leveling/) | closely related | allows the finish date to move; resource balancing also includes smoothing within float |

## Distinction

Resource levelling tends to lengthen the project duration, whereas schedule compression shortens it. Resource planning determines demand; levelling adapts the plan to actual availability. The critical chain method takes resource bottlenecks into account from the outset when determining the path that drives the end date.

## In practice

In the schedule for introducing a laboratory information system, a single validation expert is assigned to three activities running in parallel, at 250 per cent in total. The planning software places two of the activities one after the other. One of them has enough float; the other becomes critical as a result and moves the project end by one week. The project manager checks whether a second specialist could take over the simpler parts.

## Frequently asked questions

### Should levelling be left to the software?

As a proposal, yes; as a decision, no. Automatic levelling takes neither priorities nor the option of distributing work differently into account.

### What is the difference between levelling and smoothing?

Levelling removes overloads even at the price of a later end date; smoothing stays within the float and keeps the end date.

## Related terms

- [Resource planning](https://pmdecoder.com/en/glossary/resource-planning/)
- [Resource histogram](https://pmdecoder.com/en/glossary/resource-histogram/)
- [Float](https://pmdecoder.com/en/glossary/float/)
- [Schedule compression](https://pmdecoder.com/en/glossary/schedule-compression/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.