# Resource leveling

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Adjusting the schedule to available capacity](https://pmdecoder.com/en/concept/adjusting-the-schedule-to-available-capacity/)
- Topic area: [Resources and estimating](https://pmdecoder.com/en/area/resources-and-estimating/)
- Canonical version: https://pmdecoder.com/en/glossary/resource-leveling/

## Definition

In PMI usage, resource leveling is a scheduling technique in which the start and finish dates of activities are shifted so that the demand for resources does not exceed the available supply. It is usually triggered by overallocation, for example when a specialist is assigned to several activities in the same week, or when a resource is available only at certain times. Because activities may be moved beyond their float, resource leveling often extends the project duration and can change the critical path. PMI distinguishes it from resource smoothing, in which activities are moved only within their float, so that the finish date and the critical path remain unchanged, though the overallocation may not be removed entirely.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Resource levelling](https://pmdecoder.com/en/glossary/resource-levelling/) | closely related | allows the finish date to move; resource balancing also includes smoothing within float |

## Distinction

Resource leveling corresponds to the German term Ressourcenabgleich, with one qualification: in German usage, Ressourcenabgleich often also covers smoothing within float, which PMI names separately as resource smoothing. Schedule compression pursues the opposite goal, namely a shorter duration, often through more resources.

## In practice

In the schedule for a software rollout, the only database specialist is planned at 180 percent in calendar week 14. The scheduling tool proposes moving the activity “Performance tests” by eight days. Because this activity has only five days of total float, the project finish moves back by three days. The project manager presents both options to the sponsor: a later finish or external support for the tests.

## Frequently asked questions

### Does resource leveling always extend the project duration?

Not always. If the float of the moved activities is sufficient, the finish date stays the same. If an activity has to be moved beyond its float or lies on the critical path, the project becomes longer.

### Should resource leveling be left to the software?

As a proposal yes, as a decision no. Automatic procedures do not know priorities, room for negotiation or alternatives such as overtime or additional resources. The result should therefore be reviewed and adopted deliberately.

## Related terms

- [Resource levelling](https://pmdecoder.com/en/glossary/resource-levelling/)
- [Resource histogram](https://pmdecoder.com/en/glossary/resource-histogram/)
- [Critical path](https://pmdecoder.com/en/glossary/critical-path-pmi/)
- [Total float](https://pmdecoder.com/en/glossary/total-float-pmi/)
- [Schedule compression](https://pmdecoder.com/en/glossary/schedule-compression-pmi/)

---