# Resource histogram

also: Resource loading chart

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Topic area: [Resources and estimating](https://pmdecoder.com/en/area/resources-and-estimating/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/resource-histogram/

## Definition

A resource histogram plots, for a resource or group of resources over time, how much capacity is planned in each week, day or month. A horizontal line marks the available capacity. Columns above this line show overloads, deep troughs show unused capacity. The chart is an important aid for resource levelling.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

The S-curve shows cumulative values over time, the histogram the demand per time period. A utilization table contains the same information as figures but is less clear at a glance. The organization chart shows who holds which role; the histogram shows how heavily those involved are loaded.

## In practice

A construction company plans its crane operators for the next six months. The resource histogram shows a column of seven crane operators needed in March, while five are available; in May, by contrast, only three are deployed. The planners check which sites could postpone their crane work in March by a few weeks and find two building projects with sufficient float.

## Frequently asked questions

### For which resources is a histogram worthwhile?

For scarce and expensive resources where overload or idle time has noticeable consequences, such as specialists, large equipment or test rigs.

### Which time scale should be chosen?

That depends on the level of planning detail. Weeks are common for staff; for large equipment on construction sites, days are often used.

## Related terms

- [Resource levelling](https://pmdecoder.com/en/glossary/resource-levelling/)
- [Resource planning](https://pmdecoder.com/en/glossary/resource-planning/)
- [S-curve](https://pmdecoder.com/en/glossary/s-curve/)
- [Resource](https://pmdecoder.com/en/glossary/resource/)

---