# Resource breakdown structure

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.74
- Edition: ISO 21506:2024
- Concept: [Hierarchical breakdown of resources](https://pmdecoder.com/en/concept/hierarchical-breakdown-of-resources/)
- Topic area: [Resources and estimating](https://pmdecoder.com/en/area/resources-and-estimating/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/resource-breakdown-structure/

## Definition

The resource breakdown structure arranges all of a project's resources in a tree structure. The top level contains categories such as staff, machinery, materials and services, with finer groups below, such as electricians, cranes or concrete grades. The breakdown makes it easier to plan requirements, analyse costs by resource type and identify bottlenecks across several work packages.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Resource breakdown structure](https://pmdecoder.com/en/glossary/resource-breakdown-structure-pmi/) | equivalent | — |

## Distinction

The work breakdown structure breaks down the work, the resource breakdown structure the means used to carry it out. An organization chart shows people and reporting lines, the resource breakdown structure types and qualifications regardless of names. A bill of materials breaks a product down into its components, not the resources used to make it.

## In practice

An event technology company is planning a music festival with three stages. The resource breakdown structure divides staff into sound, lighting, rigging and stage construction, each with qualification levels, and equipment into loudspeakers, lighting desks, trusses and generators. The analysis shows that certified riggers are needed on all three stages at the same time and that the company's own pool is not large enough. Two riggers are booked externally at an early stage.

## Frequently asked questions

### How detailed should the resource breakdown structure be?

As detailed as resources are actually planned and procured differently. Qualifications that can substitute for each other form a single group.

### What is it used for in practice?

For requirements and capacity planning, for cost analyses by resource type and as a standard list in planning tools.

## Related terms

- [Resource](https://pmdecoder.com/en/glossary/resource/)
- [Resource planning](https://pmdecoder.com/en/glossary/resource-planning/)
- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.