# Resource breakdown structure

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Hierarchical breakdown of resources](https://pmdecoder.com/en/concept/hierarchical-breakdown-of-resources/)
- Topic area: [Resources and estimating](https://pmdecoder.com/en/area/resources-and-estimating/)
- Canonical version: https://pmdecoder.com/en/glossary/resource-breakdown-structure-pmi/

## Definition

In PMI’s understanding, the resource breakdown structure arranges all the resources a project needs in a hierarchy of categories and types. At the top level there might be labour, materials, equipment and services; below them follow finer distinctions such as skills, grades, equipment types or material groups. The structure helps to capture resource needs completely, to aggregate needs across work packages and to analyse costs by resource type. It is developed or refined when estimating resource requirements and updated during the project as new types of resources are added.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Resource breakdown structure](https://pmdecoder.com/en/glossary/resource-breakdown-structure/) | equivalent | — |

## Distinction

The resource breakdown structure corresponds to the resource breakdown structure of ISO 21506, which uses the same designation. It differs from the work breakdown structure in its subject: the latter breaks down the work, the former the means by which the work is done. The organizational breakdown structure, by contrast, shows organizational units and their responsibilities, and the risk breakdown structure organizes sources of risk; only the principle of hierarchical decomposition is shared.

## In practice

For the construction of a school canteen, the project team sets up a resource breakdown structure with the branches labour, machinery, building materials and subcontracted services. Under labour are foremen, bricklayers and electricians; under machinery are crane, excavator and vibrating plate. When the schedule is compressed, an analysis by this structure shows that in two weeks twice as many electricians are needed as are available. The team then brings in a subcontractor.

## Frequently asked questions

### How detailed should a resource breakdown structure be?

As detailed as planning and control require. If it is enough to know that electricians are needed, that level suffices; if qualifications such as high-voltage work or fire alarm systems matter, further distinctions are needed.

### Does the resource breakdown structure contain named individuals?

Usually not. It describes types of resources. Who is actually assigned is set out in resource assignments and in documents such as the responsibility assignment matrix.

## Related terms

- [Resource breakdown structure](https://pmdecoder.com/en/glossary/resource-breakdown-structure/)
- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure-pmi/)
- [Organizational breakdown structure](https://pmdecoder.com/en/glossary/organizational-breakdown-structure-pmi/)
- [Risk breakdown structure](https://pmdecoder.com/en/glossary/risk-breakdown-structure-pmi/)
- [Resource management plan](https://pmdecoder.com/en/glossary/resource-management-plan/)

---