# Residual risk

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.72
- Edition: ISO 21506:2024
- Concept: [Risk remaining after responses](https://pmdecoder.com/en/concept/risk-remaining-after-responses/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/residual-risk/

## Definition

Hardly any response eliminates a risk completely. Residual risk describes the probability and impact that are left over after mitigation, transfer or other actions. It is reassessed, documented and either explicitly accepted by an authorized body or treated further. In safety-critical industries there are often binding requirements for assessing residual risks.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Residual risk](https://pmdecoder.com/en/glossary/residual-risk-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Inherent risk is the assessment before any response, residual risk the assessment afterwards. A secondary risk only arises as a result of a response, whereas residual risk is the remaining part of the original risk. Both belong in the risk register so that the overall picture stays complete.

## In practice

A chemical company is planning a new filling line. The risk of a leak is reduced by drip trays, sensors and automatic shut-off valves. Simultaneous failure of all three systems is rated as very unlikely but serious. Plant management accepts this residual risk in writing and also has an emergency plan agreed with the local fire brigade. Whenever the plant is modified, the assessment is checked to see whether it still applies.

## Frequently asked questions

### Who accepts residual risks?

The body that has to answer for the consequences; for significant residual risks, the client or senior management.

### Can residual risk be zero?

Rarely in practice. Only avoidance eliminates a risk completely, and even that can create new risks. More important than a value of zero is that the remaining risk is known and consciously borne.

## Related terms

- [Secondary risk](https://pmdecoder.com/en/glossary/secondary-risk/)
- [Risk mitigation](https://pmdecoder.com/en/glossary/risk-mitigation/)
- [Risk acceptance](https://pmdecoder.com/en/glossary/risk-acceptance/)
- [Risk](https://pmdecoder.com/en/glossary/risk/)

---