# Residual risk

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Risk remaining after responses](https://pmdecoder.com/en/concept/risk-remaining-after-responses/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/residual-risk-pmi/

## Definition

PMI uses the term residual risk for the risk left over once the planned responses have been put in place. Hardly any action removes a risk completely; it usually reduces probability or impact to a level the organization considers acceptable. This remainder is consciously accepted, documented and monitored further. For residual risks that could still have a noticeable effect, projects often provide contingency plans or a share of the contingency reserve. Assessing the remaining risk also shows whether a response is sufficient or whether further responses are needed to bring the risk below the organization’s thresholds.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Residual risk](https://pmdecoder.com/en/glossary/residual-risk/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Risk](https://pmdecoder.com/en/glossary/risk-pmi/)

## Distinction

Residual risk corresponds to the residual risk of ISO 21506, which uses the same designation. It must be clearly separated from secondary risk, which is only caused by a risk response and is therefore a new risk, not the remainder of the original one. Both are recorded in the risk register, but for different reasons.

## In practice

A data centre project addresses the risk of a power failure with an uninterruptible power supply and a standby generator. The residual risk is that both fail at the same time, for example through a maintenance error. The probability is rated very low, the impact high. The team accepts the residual risk but prepares a contingency plan with emergency contacts and a sequence for shutting down systems.

## Frequently asked questions

### Does a residual risk have to be documented?

Yes. Only then is it clear which risk the organization is deliberately bearing and who decided so. In addition, the residual risk may grow later if conditions change.

### Who decides whether a residual risk is acceptable?

The yardstick is the organization’s risk thresholds. Within these limits the project manager can decide; beyond them, usually the sponsor or a steering body.

## Related terms

- [Residual risk](https://pmdecoder.com/en/glossary/residual-risk/)
- [Secondary risk](https://pmdecoder.com/en/glossary/secondary-risk-pmi/)
- [Risk response](https://pmdecoder.com/en/glossary/risk-response-pmi/)
- [Risk acceptance](https://pmdecoder.com/en/glossary/risk-acceptance-pmi/)
- [Contingency reserve](https://pmdecoder.com/en/glossary/contingency-reserve/)

---