# Requestor Side

- Framework: [PM²](https://pmdecoder.com/en/framework/pm2/)
- Reference: PM²-Leitfaden 3.1, Anhang G
- Edition: PM² Guide 3.1
- Concept: [Commissioning side of a project](https://pmdecoder.com/en/concept/commissioning-side-of-a-project/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Canonical version: https://pmdecoder.com/en/glossary/requestor-side/

## Definition

PM² uses the term Requestor Side for everyone in the organization that commissions a project and later works with the solution. It includes the Project Owner, the Business Manager and the Business Implementation Group with the User Representatives. The Requestor Side sets the business objectives, describes requirements, accepts results and prepares its own organization for the change. The guide also speaks of the customer side.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Client](https://pmdecoder.com/en/glossary/client/) | closely related | in PM², covers all roles of the requesting organization, from the Project Owner to the User Representatives |

## Distinction

The Requestor Side is not the same as an external client in the contractual sense: in PM², both sides usually belong to the same organization. Its counterpart is the Provider Side, which develops and implements the solution. Requirements management as a discipline covers only part of its tasks.

## In practice

In a ministry, the department responsible for civil servants' allowances requests a new case management system. The head of department as Project Owner, an officer as Business Manager and five caseworkers in the Business Implementation Group form the Requestor Side. The IT directorate on the Provider Side develops the system, and the allowances department adapts its procedures.

## Frequently asked questions

### Why does PM² distinguish between two sides?

So that it is clear who needs the result and who delivers it. Both sides are represented in balance on the Project Steering Committee, and for every task it is clear which side has to carry it out.

### Can one person belong to both sides?

That should remain the exception, because otherwise the mutual checks between requesting and delivering are lost.

## Related terms

- [Provider Side](https://pmdecoder.com/en/glossary/provider-side/)
- [Project Owner](https://pmdecoder.com/en/glossary/project-owner/)
- [Business Manager](https://pmdecoder.com/en/glossary/business-manager/)
- [Business Implementation Group](https://pmdecoder.com/en/glossary/business-implementation-group/)
- [Client](https://pmdecoder.com/en/glossary/client/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.