# Ready for Closing

abbr. RfC

- Framework: [PM²](https://pmdecoder.com/en/framework/pm2/)
- Reference: PM²-Leitfaden 3.1, Abschnitt 7.6
- Edition: PM² Guide 3.1
- Canonical version: https://pmdecoder.com/en/glossary/ready-for-closing/

## Definition

Ready for Closing (RfC) is the last Phase Gate in PM². The Project Manager checks whether execution has reached its objectives: has all planned work been completed, have all requirements been met and have the results been delivered in full? In addition, the Project Owner must have accepted the results at least provisionally, the transition must be complete and the end users must be able to work with the results. Once this is the case, the Project Steering Committee allows the Project Manager to move the project into the Closing Phase.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Classification

- Broader term: [Phase Gate](https://pmdecoder.com/en/glossary/phase-gate/)

## Distinction

Ready for Closing is not the final acceptance of the project: the Project Owner gives that only at the end of the Closing Phase. Rather, it confirms that delivery has ended and that the follow-up work can begin.

## In practice

A project for new library software meets all requirements, but two branch libraries are still working with the old system. The Project Manager applies for Ready for Closing only after these branches have also been switched over and the User Representatives have confirmed that operations are running.

## Frequently asked questions

### Does acceptance have to be final for Ready for Closing?

No. Provisional acceptance by the Project Owner is sufficient, provided the Deliverables Acceptance Management Plan allows for it. Final approval follows at the end of the Closing Phase.

### Who approves the move into the Closing Phase?

The Project Steering Committee, on the basis of the Project Manager's assessment.

## Related terms

- [Executing Phase](https://pmdecoder.com/en/glossary/executing-phase/)
- [Closing Phase](https://pmdecoder.com/en/glossary/closing-phase-pm2/)
- [Deliverables Acceptance Management Plan](https://pmdecoder.com/en/glossary/deliverables-acceptance-management-plan/)
- [Transition Plan](https://pmdecoder.com/en/glossary/transition-plan/)

---