# Quantitative risk analysis

also: Quantitative risk assessment

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Numerical assessment of overall risk](https://pmdecoder.com/en/concept/numerical-assessment-of-overall-risk/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/quantitative-risk-analysis/

## Definition

Quantitative risk analysis expresses uncertainty in numbers. For the most important risks and uncertain estimates, probabilities and impacts are stated in euros or days, often as ranges. Methods such as simulation, expected monetary value or decision trees are used to calculate how likely it is that a date or budget will be met and how large an appropriate reserve should be.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Quantitative risk analysis](https://pmdecoder.com/en/glossary/quantitative-risk-analysis-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Risk analysis](https://pmdecoder.com/en/glossary/risk-analysis/)

## Distinction

Qualitative analysis ranks risks by levels; quantitative analysis calculates their consequences for the project as a whole. Sensitivity analysis shows which input variables move the result most. Quantitative methods produce results that are only as reliable as the input data on which they are based.

## In practice

For an offshore wind farm, the management wants to know how likely it is that commissioning will be achieved by the funding deadline. The project team enters ranges for 60 activities and models weather risks for the installation vessels. The simulation gives 55 per cent. Only with an additional chartered vessel does the figure rise to 85 per cent, and the management approves the extra cost.

## Frequently asked questions

### For which projects is a quantitative analysis worthwhile?

For large, expensive or schedule-critical undertakings in which decisions on reserves, contracts or investments depend on robust figures.

### What data does it require?

Ranges for durations and costs, probabilities for risk events and their impacts, and a model of how these interact.

## Related terms

- [Qualitative risk analysis](https://pmdecoder.com/en/glossary/qualitative-risk-analysis/)
- [Monte Carlo simulation](https://pmdecoder.com/en/glossary/monte-carlo-simulation/)
- [Expected monetary value](https://pmdecoder.com/en/glossary/expected-monetary-value/)
- [Sensitivity analysis](https://pmdecoder.com/en/glossary/sensitivity-analysis/)
- [Risk contingency reserve](https://pmdecoder.com/en/glossary/risk-contingency-reserve/)

---