# Quantitative risk analysis

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Numerical assessment of overall risk](https://pmdecoder.com/en/concept/numerical-assessment-of-overall-risk/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/quantitative-risk-analysis-pmi/

## Definition

In PMI usage, quantitative risk analysis examines numerically how the identified individual risks and other sources of uncertainty together affect the project objectives. Its focus is thus the overall project risk, for example the probability of meeting a finish date or a budget. Typical techniques are Monte Carlo simulation based on schedule and cost models, sensitivity analyses that show which risks influence the result most, and decision tree analysis. The results help to size reserves and to decide on responses to overall project risk. Because the technique requires data, tools and expertise, it is worthwhile mainly for large, complex or strategically important projects.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Quantitative risk analysis](https://pmdecoder.com/en/glossary/quantitative-risk-analysis/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Risk analysis](https://pmdecoder.com/en/glossary/risk-analysis-pmi/)

## Distinction

The PMI name means the same as the cross-framework term quantitative risk analysis. While qualitative risk analysis ranks individual risks, quantitative analysis looks at their combined effect. The expected monetary value of a single risk is not yet a quantitative risk analysis in this sense.

## In practice

For the construction of a wind farm there is a schedule with a finish date in October. The team enters three-point estimates for the key activities and models weather risks and delivery delays. The Monte Carlo simulation shows that October will be reached with only 35 percent probability, whereas a date in mid-December has 80 percent. The sensitivity analysis identifies crane availability as the largest driver; the project then secures a second crane by contract.

## Frequently asked questions

### Does every project need quantitative risk analysis?

No. For many projects qualitative analysis is sufficient. Quantitative analysis pays off when much is at stake, reliable data are available and decisions, for example on reserves or commitments, need a sound basis.

### What does a Monte Carlo simulation deliver in a project?

A distribution of possible outcomes, such as finish dates or total costs, and thus the probability of achieving certain values. It does not show which outcome will occur but how likely the various outcomes are.

## Related terms

- [Quantitative risk analysis](https://pmdecoder.com/en/glossary/quantitative-risk-analysis/)
- [Monte Carlo simulation](https://pmdecoder.com/en/glossary/monte-carlo-simulation/)
- [Sensitivity analysis](https://pmdecoder.com/en/glossary/sensitivity-analysis/)
- [Decision tree analysis](https://pmdecoder.com/en/glossary/decision-tree-analysis-pmi/)
- [Qualitative risk analysis](https://pmdecoder.com/en/glossary/qualitative-risk-analysis-pmi/)
- [Contingency reserve](https://pmdecoder.com/en/glossary/contingency-reserve/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.