# Quality Register

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Qualität
- Edition: PRINCE2 7
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/quality-register/

## Definition

In PRINCE2 the Quality Register is the overview of a project’s quality activities. For each product to be checked, it lists the intended reviews and tests, the planned and actual dates, the people involved and the result. The detailed evidence, such as review minutes, test reports or acceptance statements, is not held in the register itself; the register refers to it. The register is created during initiation, filled in as soon as plans schedule quality checks, and updated as checks take place. This makes it possible to show at any time which products demonstrably meet the agreed quality criteria and where checks are still pending or have to be repeated. The rules for this are set out in the quality management approach.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

Quality assurance and quality control describe activities; the Quality Register is the record in which the control steps for project products are logged. The quality criteria themselves are stated in the product descriptions, not in the register. The Product Register, by contrast, tracks the status of all products as a whole, not only their checks. A generic acceptance record documents a single acceptance, whereas the Quality Register brings together all checks in the project.

## In practice

For the production of a training manual, the stage plan provides for two checks: a subject-matter review by two trainers and a trial run with a pilot group. Project support enters both in the Quality Register with dates and participants. After the review, it records the result “passed with rework” and refers to the list of comments. Once the trial run has been successful the entry is closed, and the Project Board sees in the next report that the manual meets the agreed criteria.

## Frequently asked questions

### When is the Quality Register created?

During project initiation, together with the other registers. Entries are added when plans for a product provide for quality checks and are updated until the check is complete.

### Does the Quality Register contain the detailed results?

No. It records that a check took place and how it turned out, and refers to the actual quality records. These are filed separately so that the register remains easy to read.

## Related terms

- [Quality control](https://pmdecoder.com/en/glossary/quality-control/)
- [Quality assurance](https://pmdecoder.com/en/glossary/quality-assurance/)
- [Quality management](https://pmdecoder.com/en/glossary/quality-management/)
- [Formal acceptance](https://pmdecoder.com/en/glossary/formal-acceptance/)
- [Product Register](https://pmdecoder.com/en/glossary/product-register/)
- [Quality practice](https://pmdecoder.com/en/glossary/quality-practice/)
- [Quality Management Approach](https://pmdecoder.com/en/glossary/quality-management-approach/)
- [Product Description](https://pmdecoder.com/en/glossary/product-description/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.
