# Quality practice

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Qualität
- Edition: PRINCE2 7
- Concept: [Planning, assuring and controlling quality](https://pmdecoder.com/en/concept/planning-assuring-and-controlling-quality/)
- Topic area: [Quality](https://pmdecoder.com/en/area/quality/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/quality-practice/

## Definition

The quality practice describes how a PRINCE2 project ensures that its products are fit for their purpose. It has two parts. In quality planning, the customer’s quality expectations and the acceptance criteria for the overall result are recorded, and quality criteria, checking methods and responsibilities are defined for each important product. In quality control, the products are checked against these requirements, the results are documented and approvals are obtained. The basis is the quality management approach, the project product description and the product descriptions; the checks themselves are tracked in a register.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Quality management](https://pmdecoder.com/en/glossary/quality-management/) | closely related | Related to the products of a project, divided into quality planning and quality control. |

## Other terms

- Quality theme (deprecated)

## Distinction

General quality management usually concerns the whole organization. The quality practice relates to the products of a single project. PRINCE2 separates quality assurance, which checks independently of the project whether the organization’s standards are being met, from project assurance, through which the project board forms its own view of the project.

## In practice

For a new claims form at an insurance company, the senior user agrees that customers must be able to complete the form without help in no more than ten minutes. This criterion is included in the project product description. For the sub-product “completion guide”, the product description specifies that five test persons from the customer base check it. The test results are recorded before the senior user approves the product.

## Frequently asked questions

### Who defines the quality expectations?

The user side, represented by the senior user. They know what the result is needed for. The supplier side contributes what can be achieved with the means provided.

### Is a checked product automatically approved?

No. The check shows whether the criteria are met; approval is a separate decision by the persons named for it, based on the check results.

## Related terms

- [Quality Management Approach](https://pmdecoder.com/en/glossary/quality-management-approach/)
- [Product Description](https://pmdecoder.com/en/glossary/product-description/)
- [Project Product Description](https://pmdecoder.com/en/glossary/project-product-description/)
- [Quality management](https://pmdecoder.com/en/glossary/quality-management/)
- [Quality assurance](https://pmdecoder.com/en/glossary/quality-assurance/)
- [Quality control](https://pmdecoder.com/en/glossary/quality-control/)
- [Quality Register](https://pmdecoder.com/en/glossary/quality-register/)
- [Focus on products principle](https://pmdecoder.com/en/glossary/focus-on-products-principle/)

---