# Quality management plan

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Setting quality objectives and checks](https://pmdecoder.com/en/concept/setting-quality-objectives-and-checks/)
- Topic area: [Quality](https://pmdecoder.com/en/area/quality/)
- Canonical version: https://pmdecoder.com/en/glossary/quality-management-plan/

## Definition

In PMI terms, the quality management plan is a component of the project management plan. It sets out how the organization's applicable policies, procedures and guidelines are put into practice on the project so that the quality objectives are met. Typical contents are the relevant quality standards, the project's quality objectives, roles and responsibilities, the deliverables and processes subject to review, planned control and assurance activities, tools used, and how nonconformances and improvements are handled. Its scope and formality depend on the needs of the project.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | [Quality Management Approach](https://pmdecoder.com/en/glossary/quality-management-approach/) | partially overlapping | Defines standards, procedures and responsibilities; the quality criteria of individual products are in the product descriptions. |
| Six Sigma | [Control plan](https://pmdecoder.com/en/glossary/control-plan/) | partially overlapping | Sets monitoring and reactions for a running process after the project, not quality assurance of the project results. |
| cross-framework | [Quality planning](https://pmdecoder.com/en/glossary/quality-planning/) | partially overlapping | denotes the document in which the result of quality planning is recorded |

## Classification

- Broader term: [Project management plan](https://pmdecoder.com/en/glossary/project-management-plan/)

## Distinction

The quality management plan is the output of what is known across frameworks as quality planning; the term refers to the document, not the activity. It sets rules and standards, whereas quality audit and quality control check compliance and results respectively. Acceptance criteria for individual deliverables are more likely to be held in requirements and scope documents.

## In practice

For the construction of a day-care centre, the quality management plan specifies the building regulations and sound insulation values to be met, a site manager responsible for quality inspections, recorded acceptance of each trade, a quality audit after the shell is complete, and a procedure for recording, assigning and tracking defects.

## Frequently asked questions

### Who prepares the quality management plan?

The project manager is accountable for it and develops it with the team and experts, often supported by the quality department. It is approved as part of the project management plan.

### Does the quality management plan have to invent its own standards?

No. It usually draws on existing standards, industry requirements and company policies and describes how they are applied on the specific project.

## Related terms

- [Quality planning](https://pmdecoder.com/en/glossary/quality-planning/)
- [Project management plan](https://pmdecoder.com/en/glossary/project-management-plan/)
- [Quality audit](https://pmdecoder.com/en/glossary/quality-audit/)
- [Cost of quality](https://pmdecoder.com/en/glossary/cost-of-quality-pmi/)
- [Acceptance criteria](https://pmdecoder.com/en/glossary/acceptance-criteria-pmi/)
- [Quality assurance](https://pmdecoder.com/en/glossary/quality-assurance/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.