# Quality Management Approach

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Qualität
- Edition: PRINCE2 7
- Concept: [Setting quality objectives and checks](https://pmdecoder.com/en/concept/setting-quality-objectives-and-checks/)
- Topic area: [Quality](https://pmdecoder.com/en/area/quality/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/quality-management-approach/

## Definition

The quality management approach describes how a PRINCE2 project puts the quality practice into effect. It names the applicable quality standards and procedures, such as requirements of the organization, the customer or relevant standards, and specifies how quality checks are planned, carried out and documented. It also records who is responsible for quality in the project, which tools are used and how quality assurance outside the project is involved. The approach is created during initiation on the basis of the quality expectations in the project product description and becomes part of the project initiation documentation. The quality criteria of individual products, by contrast, are set out in their product descriptions.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Quality management plan](https://pmdecoder.com/en/glossary/quality-management-plan/) | partially overlapping | denotes the document in which the result of quality planning is recorded |
| Six Sigma | [Control plan](https://pmdecoder.com/en/glossary/control-plan/) | partially overlapping | Sets monitoring and reactions for a running process after the project, not quality assurance of the project results. |
| cross-framework | [Quality planning](https://pmdecoder.com/en/glossary/quality-planning/) | partially overlapping | Defines standards, procedures and responsibilities; the quality criteria of individual products are in the product descriptions. |

## Distinction

The PMI quality management plan has a similar purpose. An organization’s quality manual applies to all undertakings, the quality management approach only to the one project, and it can refer to the manual. It describes rules, not the results of individual checks.

## In practice

A medical technology manufacturer is developing a new blood pressure monitor. The quality management approach refers to the company’s certified quality management system and the regulatory requirements for medical devices. It specifies that every design document is checked by a second person, that the clinical evaluation is reviewed by an external body and that the quality department carries out spot checks on compliance.

## Frequently asked questions

### Who approves the quality management approach?

The project board, as part of the project initiation documentation. The senior user makes sure that the users’ quality expectations are covered.

### Does a project have to develop its own quality standards?

Usually not. The approach builds on existing standards of the organization or the customer and only adds what applies additionally to the project.

## Related terms

- [Quality practice](https://pmdecoder.com/en/glossary/quality-practice/)
- [Product Description](https://pmdecoder.com/en/glossary/product-description/)
- [Quality planning](https://pmdecoder.com/en/glossary/quality-planning/)
- [Quality management plan](https://pmdecoder.com/en/glossary/quality-management-plan/)
- [Quality assurance](https://pmdecoder.com/en/glossary/quality-assurance/)
- [Quality Register](https://pmdecoder.com/en/glossary/quality-register/)
- [Project Product Description](https://pmdecoder.com/en/glossary/project-product-description/)
- [Sustainability Management Approach](https://pmdecoder.com/en/glossary/sustainability-management-approach/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.