# Qualitative risk analysis

also: Qualitative risk assessment

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Rating risks by probability and impact](https://pmdecoder.com/en/concept/rating-risks-by-probability-and-impact/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/qualitative-risk-analysis/

## Definition

In qualitative risk analysis, those involved estimate for each risk how likely it is to occur and how severe its effect would be, usually on scales such as low, medium and high or from one to five. Combining the two produces a ranking, often shown in a risk matrix. Urgency, controllability or how soon the risk could occur may also be taken into account.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Qualitative risk analysis](https://pmdecoder.com/en/glossary/qualitative-risk-analysis-pmi/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Risk analysis](https://pmdecoder.com/en/glossary/risk-analysis/)

## Distinction

Quantitative risk analysis works with numerical values such as euros, days or probabilities and determines the effects on the project as a whole. Qualitative analysis is quicker and suitable for almost all projects, but it remains subjective. It is usually carried out first and decides which risks are examined in more depth quantitatively.

## In practice

A project team for the refurbishment of a hotel rates 35 risks on a scale from one to five. A fire safety defect in the old building is given probability three and impact five; a delay in furniture deliveries probability four and impact two. At first the team argues over the ratings, then it agrees on described levels, for example impact five meaning a delay of more than four weeks. After that, the assessment proceeds quickly.

## Frequently asked questions

### Why should the scales be described?

So that everyone understands the same thing by “high”. Described levels, for example in ranges of euros or days, make ratings comparable.

### How often is the qualitative analysis repeated?

Regularly during the project, because probabilities and impacts change as work progresses.

## Related terms

- [Quantitative risk analysis](https://pmdecoder.com/en/glossary/quantitative-risk-analysis/)
- [Risk matrix](https://pmdecoder.com/en/glossary/risk-matrix/)
- [Risk register](https://pmdecoder.com/en/glossary/risk-register/)
- [Risk management](https://pmdecoder.com/en/glossary/risk-management/)

---