# Qualitative risk analysis

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Rating risks by probability and impact](https://pmdecoder.com/en/concept/rating-risks-by-probability-and-impact/)
- Topic area: [Risks and opportunities](https://pmdecoder.com/en/area/risks-and-opportunities/)
- Canonical version: https://pmdecoder.com/en/glossary/qualitative-risk-analysis-pmi/

## Definition

In PMI usage, qualitative risk analysis serves to prioritize the identified individual project risks so that the team can focus on the most important ones. To this end, the probability and impact of each risk are rated on agreed scales, often with a probability and impact matrix. Further characteristics can also be considered, such as urgency, proximity, manageability, detectability or connections with other risks. The quality of the available information is assessed as well, because uncertain data distort the ratings. The results are a ranking, assigned owners and updated entries in the risk register. Earlier editions of the PMBOK Guide described this analysis as a process of its own.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Qualitative risk analysis](https://pmdecoder.com/en/glossary/qualitative-risk-analysis/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: [Risk analysis](https://pmdecoder.com/en/glossary/risk-analysis-pmi/)

## Distinction

The PMI name means the same as the cross-framework term qualitative risk analysis. Quantitative risk analysis builds on it, works with numbers and considers the combined effect of all risks. The probability and impact matrix is a tool of qualitative analysis, not the analysis itself.

## In practice

After a risk identification workshop, the risk register for relocating a warehouse contains 48 risks. In a two-hour session the core team rates each risk on the agreed five-point scales and marks those that could occur within the next three months. Twelve risks fall into the red zone, and five of them are also urgent. Owners are named for these at once; three are earmarked for quantitative analysis.

## Frequently asked questions

### How often should qualitative risk analysis be repeated?

Regularly throughout the project, for example at fixed intervals or at phase transitions, and whenever new risks are identified or the situation changes. Ratings become outdated because probability and impact change as the project progresses.

### How can subjective ratings be improved?

Through clear definitions of the scale levels, involving several people, making assumptions explicit and assessing data quality. This shows where a rating stands on firm ground and where it does not.

## Related terms

- [Qualitative risk analysis](https://pmdecoder.com/en/glossary/qualitative-risk-analysis/)
- [Probability and impact matrix](https://pmdecoder.com/en/glossary/probability-and-impact-matrix/)
- [Quantitative risk analysis](https://pmdecoder.com/en/glossary/quantitative-risk-analysis-pmi/)
- [Risk register](https://pmdecoder.com/en/glossary/risk-register-pmi/)
- [Risk analysis](https://pmdecoder.com/en/glossary/risk-analysis-pmi/)

---