# Pull system

- Framework: [Kanban](https://pmdecoder.com/en/framework/kanban/)
- Reference: Kanban Guide 2025.5, Abschnitt Actively Managing Items in a Workflow
- Edition: The Kanban Guide, May 2025
- Concept: [Starting work only on demand or when capacity is free](https://pmdecoder.com/en/concept/starting-work-only-on-demand-or-when-capacity-is-free/)
- Topic area: [Approaches and agility](https://pmdecoder.com/en/area/approaches-and-agility/)
- Canonical version: https://pmdecoder.com/en/glossary/pull-system/

## Definition

In a pull system, work is not assigned as soon as it arises but pulled when capacity becomes free. The Kanban Guide describes the pull system as a consequence of limiting work in progress: the members only start a new work item when a clear signal shows that they can handle it, for example because less work is in progress than the agreed limit allows. They should avoid pulling more items into a part of the process than are allowed there. Pulling or selecting new work thus becomes a deliberate decision. A pull system reduces waiting times and overload and makes visible where work is piling up.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| Lean | [Pull principle](https://pmdecoder.com/en/glossary/pull-principle/) | closely related | In Kanban applied to knowledge work; the signal results from limiting work in progress rather than from consumption at downstream stages. |

## Classification

- Broader term: [Kanban practices](https://pmdecoder.com/en/glossary/kanban-practices/)

## Distinction

In a push system, work is fed into a process according to plan or on request, regardless of whether capacity is available. The pull principle of lean management and the Toyota Production System controls the replenishment of materials in the same way; there, kanban cards were originally the signals that triggered replenishment.

## In practice

In an advertising agency, new client jobs used to land directly with the graphic designers, who often had ten jobs in parallel. The agency introduces a pull system: jobs wait in a "ready" column, and a designer only pulls a new one when one of his or her three jobs at most moves on to client review. Account management can now see how many jobs are waiting and can give clients realistic dates.

## Frequently asked questions

### Who decides which item is pulled?

The members of the Kanban system, according to the agreed policies, for example by urgency or value. The Kanban Guide does not prescribe any particular order.

### Are there exceptions to pulling?

Possibly, but they should be explicitly agreed. The Kanban Guide requires permitted exceptions to the limit on work in progress to be included in the Definition of Workflow.

## Related terms

- [Work in Progress](https://pmdecoder.com/en/glossary/work-in-progress/)
- [Flow](https://pmdecoder.com/en/glossary/flow/)
- [Kaizen](https://pmdecoder.com/en/glossary/kaizen/)

## Differences from other editions

- The Kanban Guide, December 2020: The guide presented the pull system as a by-product of the WIP limits. Pulling more items than the limit allowed was intended only in rare cases and with the agreement of the members.

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.