# Project Work Plan

- Framework: [PM²](https://pmdecoder.com/en/framework/pm2/)
- Reference: PM²-Leitfaden 3.1, Abschnitt 6.4
- Edition: PM² Guide 3.1
- Canonical version: https://pmdecoder.com/en/glossary/project-work-plan/

## Definition

The Project Work Plan refines the scope of a PM² project and organizes the work and the deliverables. It consists of three parts: the work breakdown structure with the hierarchical breakdown of all work, the estimates of effort and costs taking available resources into account, and the schedule with dependencies and start and end dates. The Project Manager coordinates its preparation with the Project Core Team. Once approved, it serves as the baseline, but it is continuously updated so that work arising later, such as actions to address risks, is also captured.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

The Project Work Plan is broader than a pure schedule because it also contains the breakdown and the estimates, but narrower than the project management plan of other frameworks: the management rules are in the Project Handbook. The Project Work Plan also covers the activities for transition and business implementation.

## In practice

For the renewal of a data centre, the core team breaks the work down into 38 work packages, estimates them with three-point estimates and schedules them in a bar chart covering eleven months. After approval, the Project Manager freezes this version as the baseline; a fire safety inspection decided on later is added as a new work package.

## Frequently asked questions

### What parts does the Project Work Plan consist of?

The work breakdown structure, the effort and cost estimates and the project schedule.

### May the Project Work Plan be changed after approval?

It should stay current and take in new work. The approved version serves as the baseline for detecting deviations; larger changes go through change management.

## Related terms

- [Project Handbook](https://pmdecoder.com/en/glossary/project-handbook/)
- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure/)
- [Project schedule](https://pmdecoder.com/en/glossary/project-schedule/)
- [Baseline](https://pmdecoder.com/en/glossary/baseline/)
- [Planning Phase](https://pmdecoder.com/en/glossary/planning-phase/)

---