# Project Steering Committee

abbr. PSC

- Framework: [PM²](https://pmdecoder.com/en/framework/pm2/)
- Reference: PM²-Leitfaden 3.1, Abschnitt 4.4
- Edition: PM² Guide 3.1
- Concept: [Steering body of a project](https://pmdecoder.com/en/concept/steering-body-of-a-project/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Canonical version: https://pmdecoder.com/en/glossary/project-steering-committee/

## Definition

The Project Steering Committee (PSC) brings together the roles that steer and direct a PM² project and ensures a balance between the requesting and the delivering side. It is chaired by the Project Owner. The committee keeps the project aligned with its objectives, ensures compliance with the organization's rules, approves important artefacts such as the Project Charter and the Project Work Plan, decides on major changes and resolves issues that the team cannot settle on its own. It also authorizes moving from one phase to the next, except where the Appropriate Governance Body does so.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Steering committee](https://pmdecoder.com/en/glossary/steering-committee-pmi/) | closely related | fixed membership chaired by the Project Owner, with the Solution Provider and other roles |
| PRINCE2 | [Project Board](https://pmdecoder.com/en/glossary/project-board/) | closely related | Composed of Executive, Senior User and Senior Supplier; the Executive has the final say. |
| cross-framework | [Steering committee](https://pmdecoder.com/en/glossary/steering-committee/) | closely related | fixed membership chaired by the Project Owner, with the Solution Provider and other roles |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The general term steering committee describes the same principle without fixed membership. PM², by contrast, defines permanent members and names optional roles such as the User Representatives, a contractor's project manager or project quality assurance. It differs from the Appropriate Governance Body in focusing on an individual project rather than the portfolio.

## In practice

For the replacement of an HR administration system, the Project Steering Committee meets monthly. Alongside the Project Owner from the HR department, its members are the Solution Provider from IT, the Business Manager and the Project Manager; the data protection officer is called in for data protection questions. Approval of the Executing Phase is postponed until the Transition Plan covers the period in which both systems run in parallel.

## Frequently asked questions

### Who are the permanent members of the Project Steering Committee?

The roles of the Directing and Managing Layers are permanently represented: Project Owner, Solution Provider, Business Manager and Project Manager. Other roles are added depending on the project.

### Which decisions belong to the committee?

Everything that significantly affects the project's objectives or its ability to act: Phase Gates, important documents, larger change requests and escalated issues.

## Related terms

- [Steering committee](https://pmdecoder.com/en/glossary/steering-committee/)
- [Project Owner](https://pmdecoder.com/en/glossary/project-owner/)
- [Appropriate Governance Body](https://pmdecoder.com/en/glossary/appropriate-governance-body/)
- [Steering Layer](https://pmdecoder.com/en/glossary/steering-layer/)
- [Phase Gate](https://pmdecoder.com/en/glossary/phase-gate/)

---