# Project scope

also: Scope

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.69
- Edition: ISO 21506:2024
- Concept: [Totality of results and work to be delivered](https://pmdecoder.com/en/concept/totality-of-results-and-work-to-be-delivered/)
- Topic area: [Scope and requirements](https://pmdecoder.com/en/area/scope-and-requirements/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/project-scope/

## Definition

Project scope describes what is created in the project and what work is needed to create it. ISO 21506 puts the emphasis on the approved work that is intended to achieve the agreed objectives: anything that has not been approved is not part of the scope. In practice, a further distinction is made between product scope, meaning the features and functions of the result, and work scope, meaning the activities required to produce it. A good scope description also includes a list of what is explicitly excluded.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Project scope](https://pmdecoder.com/en/glossary/project-scope-pmi/) | equivalent | — |
| PRINCE2 | [Project Product Description](https://pmdecoder.com/en/glossary/project-product-description/) | partially overlapping | Describes the overall output with quality expectations and acceptance criteria, not the work. |

## Distinction

The project objective states what a project is for, the project scope what is delivered to achieve it. The work breakdown structure divides the scope into manageable parts. Creeping, unapproved extensions of scope are known as scope creep, whereas approved changes go through change control.

## In practice

A museum commissions the design of an exhibition on the history of its city. The scope includes the concept, exhibition architecture, texts in two languages, six media stations and an accompanying booklet. An audio guide, a website and loans from other museums are explicitly excluded. When the director asks about an audio guide during implementation, the project manager refers to this list and submits a quote as a change instead of quietly taking on the work.

## Frequently asked questions

### Why record what is not part of the scope?

Because misunderstandings rarely arise from the items that are listed, but from things that each side takes for granted.

### How do product scope and work scope differ?

Product scope describes the result, work scope the route to it. Training can be part of the work scope without being part of the product.

## Related terms

- Project objective
- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure/)
- [Requirement](https://pmdecoder.com/en/glossary/requirement/)
- [Deliverable](https://pmdecoder.com/en/glossary/deliverable/)
- [Scope creep](https://pmdecoder.com/en/glossary/scope-creep/)

---