# Project schedule

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Timing of project work](https://pmdecoder.com/en/concept/timing-of-project-work/)
- Topic area: [Scheduling](https://pmdecoder.com/en/area/scheduling/)
- Canonical version: https://pmdecoder.com/en/glossary/project-schedule-pmi/

## Definition

In PMI usage, the project schedule is the result of a schedule model; it shows interlinked activities with their durations, planned dates, milestones and resources. PMI distinguishes the schedule model, meaning the data maintained in a tool with activities, dependencies, durations and calendars, from its presentation as the project schedule. Depending on the purpose, it is presented as a Gantt chart, a milestone schedule or a network diagram. An approved version serves as the schedule baseline against which actual progress is measured; changes to it go through change control.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Project schedule](https://pmdecoder.com/en/glossary/project-schedule/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Classification

- Narrower terms: [Milestone schedule](https://pmdecoder.com/en/glossary/milestone-schedule/)

## Distinction

The cross-framework schedule refers to the same thing; this entry gives the PMI view. The milestone schedule is a condensed form, the Gantt chart a type of presentation. The schedule baseline is the approved version, whereas the current project schedule shows the latest planning status including forecasts.

## In practice

For the construction of a new day-care centre, the planning office maintains a schedule model with 140 activities. Three views are produced from it: a detailed project schedule for site management, a Gantt chart by trade for the site meeting and a milestone schedule for the operator. After approval, the version is saved as the baseline; every week actual dates are recorded and variances reported.

## Frequently asked questions

### What is the difference between the schedule model and the project schedule?

The schedule model is the underlying data with activities, dependencies, durations and calendars. The project schedule is what is calculated from it and presented for a particular purpose.

### How often should the project schedule be updated?

At a fixed interval that matches the reporting cycle, usually weekly or fortnightly, and additionally after approved changes. Outdated schedules quickly lose their value for control.

## Related terms

- [Project schedule](https://pmdecoder.com/en/glossary/project-schedule/)
- [Activity](https://pmdecoder.com/en/glossary/activity-pmi/)
- [Gantt chart](https://pmdecoder.com/en/glossary/gantt-chart-pmi/)
- [Milestone schedule](https://pmdecoder.com/en/glossary/milestone-schedule/)
- [Critical path](https://pmdecoder.com/en/glossary/critical-path-pmi/)
- [Baseline](https://pmdecoder.com/en/glossary/baseline/)

---