# Project schedule network diagram

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Diagram of activities and their dependencies](https://pmdecoder.com/en/concept/diagram-of-activities-and-their-dependencies/)
- Topic area: [Network planning](https://pmdecoder.com/en/area/network-planning/)
- Canonical version: https://pmdecoder.com/en/glossary/project-schedule-network-diagram/

## Definition

The project schedule network diagram shows the activities of a project and their logical relationships as a connected network. It makes visible the order in which the work must be performed, which activities can run in parallel and where paths converge. Today it is almost always created with the precedence diagramming method, with activities as nodes and relationships as arrows. Depending on the purpose, the nodes contain only the activity name or also duration, early and late dates and float. The diagram can show the whole project or a part of it.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Network schedule](https://pmdecoder.com/en/glossary/network-schedule/) | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The project schedule network diagram corresponds to the network schedule (Netzplan) in ISO 21506. A Gantt chart, by contrast, shows activities as bars on a time axis, with dependencies drawn in only as a supplement. The project schedule is the broader output of scheduling, which can be presented in various forms, including as a network diagram.

## In practice

Before a project to merge two municipal utilities begins, the project manager prints the project schedule network diagram on a large poster. In a workshop, the sub-project leads walk through the arrows and find two missing dependencies: the tariff changeover needs the completed customer database, and the works agreement must be in place before the duty rosters are changed.

## Frequently asked questions

### When is a network diagram better than a bar chart?

When dependencies are the focus, for example when building or reviewing the schedule logic. For the question of what happens when, a bar chart is usually easier to read.

### Must the network diagram show all activities?

No. For meetings, a condensed network with summary activities or milestones is often enough. The complete logic remains stored in the scheduling tool.

## Related terms

- [Network schedule](https://pmdecoder.com/en/glossary/network-schedule/)
- [Precedence diagramming method](https://pmdecoder.com/en/glossary/precedence-diagramming-method/)
- [Logical relationship](https://pmdecoder.com/en/glossary/logical-relationship-pmi/)
- [Project schedule](https://pmdecoder.com/en/glossary/project-schedule-pmi/)
- [Gantt chart](https://pmdecoder.com/en/glossary/gantt-chart/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.