# Project role

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/project-role/

## Definition

A project role describes what is expected of someone in the project, regardless of who fills the role. Typical roles are client, project manager, sub-project manager, subject matter expert or quality officer. Each role comprises tasks, the authority needed for them and responsibility for particular results.

## Equivalents in other frameworks

No equivalents have been recorded for this term yet.

## Distinction

A role is not a position: a position is permanently anchored in the line organization, whereas a project role exists only within the project. One person can hold several roles, and one role can be shared among several people. Responsibility denotes the obligation to answer for a result, authority the right to act on it; the role combines both with the tasks.

## In practice

In a research project at a university, a postdoctoral researcher takes on both the leadership of a work package and data protection for the project. At the start, a half-page description is drawn up for each role. When she goes abroad for a year, the data protection role can be filled again without a lengthy handover, because it is documented which duties and decision-making rights belong to it.

## Frequently asked questions

### Why plan with roles rather than names?

Because people change, but the tasks remain. Role descriptions make deputizing and replacement easier.

### What does the principle of congruence state?

The tasks, authority and responsibility of a role should match. Anyone who is responsible for a result also needs the rights to bring it about.

## Related terms

- [Delegated authority](https://pmdecoder.com/en/glossary/delegated-authority/)
- [Responsibility assignment matrix](https://pmdecoder.com/en/glossary/responsibility-assignment-matrix/)
- [Organization chart](https://pmdecoder.com/en/glossary/organization-chart/)
- [Project manager](https://pmdecoder.com/en/glossary/project-manager/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.