# Project Progress Report

- Framework: [PM²](https://pmdecoder.com/en/framework/pm2/)
- Reference: PM²-Leitfaden 3.1, Anhang G
- Edition: PM² Guide 3.1
- Concept: [Regular project status report](https://pmdecoder.com/en/concept/regular-project-status-report/)
- Topic area: [Stakeholders and communication](https://pmdecoder.com/en/area/stakeholders-and-communication/)
- Canonical version: https://pmdecoder.com/en/glossary/project-progress-report/

## Definition

With the Project Progress Report, the Project Manager tells the Project Steering Committee in PM² where the project stands, measured against the Project Charter and the baselines. It reports on the state of the deliverables, the effort spent, risks and important issues, ongoing actions, achievements and changes to scope. Frequency and format are set in the communications management plan. Besides this more detailed report, PM² provides the brief Project Status Report, a one-page summary that is sent out considerably more often.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Progress report](https://pmdecoder.com/en/glossary/progress-report/) | closely related | defined PM² artefact from the Project Manager to the Project Steering Committee |
| PRINCE2 | [Highlight Report](https://pmdecoder.com/en/glossary/highlight-report/) | closely related | Report from the Project Manager to the Project Board per management stage, geared to management by exception. |
| PRINCE2 | [Checkpoint Report](https://pmdecoder.com/en/glossary/checkpoint-report/) | partially overlapping | Progress report at work package level from the Team Manager to the Project Manager. |

## Distinction

The Project Status Report summarizes the status on one page and is issued more frequently; the Project Progress Report is more detailed and compares systematically against the plans. The general term status report covers both forms.

## In practice

In a project to modernize specialist IT procedures, the Project Steering Committee receives a one-page status report with traffic lights every month and a Project Progress Report every three months. The latter shows that two of five modules have been accepted, that effort is eight percent above plan and that a change request has extended the scope by a reporting module.

## Frequently asked questions

### How often is the Project Progress Report prepared?

This is set in the communications management plan. The interval is usually longer than for the Project Status Report, which appears roughly every one to two months.

### Who reads the report?

Primarily the Project Steering Committee; depending on the communication plan, other stakeholders also receive it.

## Related terms

- [Progress report](https://pmdecoder.com/en/glossary/progress-report/)
- [Project Steering Committee](https://pmdecoder.com/en/glossary/project-steering-committee/)
- [Monitor & Control](https://pmdecoder.com/en/glossary/monitor-and-control/)
- [Project reporting](https://pmdecoder.com/en/glossary/project-reporting/)

---