# Project plan

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Comprehensive project management plan](https://pmdecoder.com/en/concept/comprehensive-project-management-plan/)
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/project-plan/

## Definition

In everyday usage, in German-speaking settings as elsewhere, “project plan” usually refers to time planning: an overview of the activities with their durations, sequence and dates, often drawn as a bar chart with the milestones marked. Some people also include responsibilities or a rough cost frame; there is no fixed boundary. This is what makes the term tricky: in ISO 21506, the same name denotes a document that brings together all baselines and subsidiary plans of a project, from scope and cost to risk and communication, and in the PMBOK Guide the equivalent is the project management plan. This entry covers the colloquial usage and the risk of confusion that comes with it.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Project plan](https://pmdecoder.com/en/glossary/project-plan-iso/) | false friend | The project management plan comprises all subsidiary plans, including scope, schedule, cost, quality, risk and communication. Anyone who says “Projektplan” in German almost always means just the schedule. In international projects, this confusion regularly leads to misunderstandings about the scope of delivery. |
| PMI / PMBOK Guide | [Project management plan](https://pmdecoder.com/en/glossary/project-management-plan/) | false friend | The project management plan comprises all subsidiary plans, including scope, schedule, cost, quality, risk and communication. Anyone who says “Projektplan” in German almost always means just the schedule. In international projects, this confusion regularly leads to misunderstandings about the scope of delivery. |
| PRINCE2 | [Project Initiation Documentation](https://pmdecoder.com/en/glossary/project-initiation-documentation/) | false friend | The project management plan comprises all subsidiary plans, including scope, schedule, cost, quality, risk and communication. Anyone who says “Projektplan” in German almost always means just the schedule. In international projects, this confusion regularly leads to misunderstandings about the scope of delivery. |
| PRINCE2 | [Project Plan](https://pmdecoder.com/en/glossary/project-plan-prince2/) | false friend | Despite the name, not the comprehensive plan: the PRINCE2 project plan is only one part of the project initiation documentation and covers products, stages, dates and costs at a high level. |
| PM² | [Project Handbook](https://pmdecoder.com/en/glossary/project-handbook/) | false friend | The project management plan comprises all subsidiary plans, including scope, schedule, cost, quality, risk and communication. Anyone who says “Projektplan” in German almost always means just the schedule. In international projects, this confusion regularly leads to misunderstandings about the scope of delivery. |
| ISO 21506 | Project management plan | closely related | corresponds to the PMI understanding |

## Distinction

The schedule is what everyday usage usually has in mind; calling it by that name avoids misunderstandings. The project plan under ISO 21506 and the PMI project management plan cover all subsidiary plans and share only the name with the everyday term. A milestone plan shows just the key dates, and a Gantt chart is a form of presentation rather than a plan of its own. The PRINCE2 Project Plan is likewise a planning term at project level that goes beyond a pure schedule.

## In practice

A German machine builder is working on a custom production line for a customer in the United States. The contract requires a “project plan” after four weeks. The project manager sends a carefully maintained bar chart with 120 activities. The customer objects: they had also expected statements on budget, risks, quality inspections and reporting lines. Both sides then agree on a list of contents for the document, and within the project the bar chart is from now on called the schedule.

## Frequently asked questions

### What does “project plan” mean in everyday usage?

Usually it means the schedule, often shown as a bar chart: which activities take place when, and which milestones there are. Other plans such as cost, risk or communication planning are rarely included.

### Why does the term cause misunderstandings?

In the PMBOK Guide, the project management plan comprises all subsidiary plans of the project. When someone in a German-speaking setting says “Projektplan”, the other side in an international project may therefore expect a far more comprehensive document than the one delivered.

### How can the confusion be avoided?

Most simply by naming precisely what is meant: schedule for time planning, project management plan for the overall document. Where that is not possible, a short clarification at the start of the project about what the project plan should contain helps.

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.