# Project Plan

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Pläne
- Edition: PRINCE2 7
- Concept: [Comprehensive project management plan](https://pmdecoder.com/en/concept/comprehensive-project-management-plan/)
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/project-plan-prince2/

## Definition

In PRINCE2, the project plan is the plan for the entire project. At a high level it shows which major products are created, into which management stages the project is divided, which milestones there are and which time, resources and costs are provided for. It also contains the project tolerances, assumptions, dependencies and the controls used to monitor progress. It is created during initiation, is part of the project initiation documentation and serves the project board as a baseline for comparison. It is updated with the actual status at each stage boundary.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Project management plan | false friend | Despite the name, not the comprehensive plan: the PRINCE2 project plan is only one part of the project initiation documentation and covers products, stages, dates and costs at a high level. |
| ISO 21506 | [Project plan](https://pmdecoder.com/en/glossary/project-plan-iso/) | false friend | Despite the name, not the comprehensive plan: the PRINCE2 project plan is only one part of the project initiation documentation and covers products, stages, dates and costs at a high level. |
| PMI / PMBOK Guide | [Project management plan](https://pmdecoder.com/en/glossary/project-management-plan/) | false friend | Despite the name, not the comprehensive plan: the PRINCE2 project plan is only one part of the project initiation documentation and covers products, stages, dates and costs at a high level. |
| PM² | [Project Handbook](https://pmdecoder.com/en/glossary/project-handbook/) | false friend | Despite the name, not the comprehensive plan: the PRINCE2 project plan is only one part of the project initiation documentation and covers products, stages, dates and costs at a high level. |
| cross-framework | [Project plan](https://pmdecoder.com/en/glossary/project-plan/) | false friend | The project management plan comprises all subsidiary plans, including scope, schedule, cost, quality, risk and communication. Anyone who says “Projektplan” in German almost always means just the schedule. In international projects, this confusion regularly leads to misunderstandings about the scope of delivery. |

## Distinction

The name is misleading: the PRINCE2 project plan is not the comprehensive PMI project management plan, nor the project plan under ISO 21506 that bundles all baselines. In PRINCE2 that role is taken by the project initiation documentation, of which the project plan is one part. Nor is it merely a schedule, as “project plan” is often understood, because it also covers products, costs and controls.

## In practice

For introducing a new payroll system, the project plan shows four stages: initiation, design, build and test, and roll-out. For each stage the major products, costs and planned end dates are given, together with a tolerance of five per cent on the total budget. The individual tasks of the design stage are not in the project plan but in the stage plan for that stage.

## Frequently asked questions

### How detailed is a project plan?

Broad enough to remain reliable for the duration of the whole project. The details are in the stage plans, each of which is produced shortly before the stage concerned.

### Who approves the project plan?

The project board, as part of the project initiation documentation. The project manager also submits updates at stage boundaries to the board.

## Related terms

- [Plans practice](https://pmdecoder.com/en/glossary/plans-practice/)
- [Stage Plan](https://pmdecoder.com/en/glossary/stage-plan/)
- [Project Initiation Documentation](https://pmdecoder.com/en/glossary/project-initiation-documentation/)
- [Project management plan](https://pmdecoder.com/en/glossary/project-management-plan/)
- [Project plan](https://pmdecoder.com/en/glossary/project-plan/)
- [Project plan](https://pmdecoder.com/en/glossary/project-plan-iso/)
- [Exception Plan](https://pmdecoder.com/en/glossary/exception-plan/)
- [Initiating a project](https://pmdecoder.com/en/glossary/initiating-a-project/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.