# Project phase

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Concept: [Defined stage of a project](https://pmdecoder.com/en/concept/defined-stage-of-a-project/)
- Topic area: [Fundamentals](https://pmdecoder.com/en/area/fundamentals/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/project-phase/

## Definition

A project phase is a coherent stretch of a project in which work with a common focus is grouped together, for example concept, design, implementation or handover. Each phase has a result of its own that shows whether it is complete, and this result forms the basis for the next phase. Dividing a project into phases makes large undertakings manageable: planning and estimating can concentrate on the next stretch, and at the phase boundaries it can be checked whether the project should continue as intended. How many phases there are and what they are called depends on the industry and the delivery approach.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Project phase](https://pmdecoder.com/en/glossary/project-phase-pmi/) | equivalent | — |
| PRINCE2 | [Management Stage](https://pmdecoder.com/en/glossary/management-stage/) | closely related | A unit of authorization and direction that need not match technical stages. |

## Distinction

The project life cycle is the whole sequence of phases, the project phase a single section of it. The gate lies at the end of a phase and is the decision point, not the section itself. An iteration or a Sprint repeats at short, fixed intervals, whereas a phase is defined by its content and is usually passed through only once. The PRINCE2 Management Stage is a unit of authorization and direction that need not match technical phases. The PMI project phase refers to the same thing.

## In practice

A city administration introduces new software for building permits and divides the project into five phases: needs analysis, tendering, set-up, pilot operation and roll-out to all departments. Each phase ends with a tangible result, such as the agreed catalogue of requirements or the report on the pilot. Because the pilot reveals that the interface to the archive system transfers documents incompletely, the project stays in this phase for three more weeks instead of starting the roll-out with a known defect.

## Frequently asked questions

### How many phases does a project have?

There is no fixed number. It depends on the industry, the delivery approach and the size of the project. Four to six phases are common, for example initiating, planning, executing and closing; PM², for instance, uses exactly these four.

### May project phases overlap?

In practice this happens when a phase starts before the previous one has been completed in order to save time. It increases risk, because work continues on results that have not yet been approved and may still change.

### How does a project phase differ from the project life cycle?

A project phase is a single section with its own result. The project life cycle describes the entire sequence of phases from the start to the end of the project.

---