# Project phase

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Defined stage of a project](https://pmdecoder.com/en/concept/defined-stage-of-a-project/)
- Topic area: [Fundamentals](https://pmdecoder.com/en/area/fundamentals/)
- Canonical version: https://pmdecoder.com/en/glossary/project-phase-pmi/

## Definition

In PMI usage a project phase is a group of logically connected activities within a project that ends when one or more deliverables are completed. Together the phases form the project life cycle. Each phase has a recognizable focus, such as concept, design or implementation, and produces results on which the next phase builds. Phases can run sequentially or overlap. At the end of a phase there is often a review at which a decision is taken on moving to the next phase, repeating the phase, making changes or terminating the project. PMI calls these decision points phase gates or phase reviews.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Project phase](https://pmdecoder.com/en/glossary/project-phase/) | equivalent | — |
| PRINCE2 | [Management Stage](https://pmdecoder.com/en/glossary/management-stage/) | closely related | A unit of authorization and direction that need not match technical stages. |

## Distinction

The ISO term project phase refers to the same thing. A phase should not be confused with an iteration: an iteration is a short, strictly time-limited cycle that repeats, whereas a phase is a section defined by its content that is usually passed through only once. A phase gate is the decision point at the end of a phase, not the phase itself.

## In practice

A pharmaceutical company divides the introduction of a new laboratory information system into the phases requirements analysis, selection, configuration and validation. Requirements analysis ends with an approved requirements specification. Only when quality assurance has accepted it does the selection of a supplier begin.

## Frequently asked questions

### How many phases should a project have?

There is no fixed rule. The number depends on size, risk and industry. Too many phases create administrative effort; too few remove opportunities to correct course.

### May phases overlap?

Yes. To save time, the next phase can begin before the previous one is fully complete. This does, however, increase the risk of rework if earlier results still change.

## Related terms

- [Project phase](https://pmdecoder.com/en/glossary/project-phase/)
- [Project life cycle](https://pmdecoder.com/en/glossary/project-life-cycle-pmi/)
- [Phase gate](https://pmdecoder.com/en/glossary/phase-gate-pmi/)
- [Deliverable](https://pmdecoder.com/en/glossary/deliverable-pmi/)
- [Gate](https://pmdecoder.com/en/glossary/gate/)

---