# Project mandate

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO/TR 21506:2018, 3.12
- Edition: ISO/TR 21506:2018 (not the current edition)
- Concept: [Formal authorization of a project](https://pmdecoder.com/en/concept/formally-authorizing-a-project/)
- Topic area: [Initiating](https://pmdecoder.com/en/area/initiating/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/project-mandate/

## Definition

Document that formally puts a project into effect, sets out its purpose and scope, and grants the project manager the necessary authority. The project mandate marks the transition from preparation to execution and is therefore the first binding decision in the course of the project. Typical contents are the reason and objectives, scope and exclusions, the budget and time frame, the names of sponsor and project manager and the decisions the project manager may take on their own.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | [Project Mandate](https://pmdecoder.com/en/glossary/project-mandate-prince2/) | false friend | In ISO 21506 “project mandate” is the binding authorization of a project; in PRINCE2 the project mandate is only the external trigger that starts preparation. |
| PMI / PMBOK Guide | [Project charter](https://pmdecoder.com/en/glossary/project-charter/) | equivalent | — |
| PM² | [Project Charter](https://pmdecoder.com/en/glossary/project-charter-pm2/) | closely related | forms the basis for approval together with the business case; the project manager has already been appointed |
| Six Sigma | [Six Sigma project charter](https://pmdecoder.com/en/glossary/six-sigma-project-charter/) | closely related | Tailored to an improvement project with a measurable output, usually shorter and still updated during the first phases. |
| PRINCE2 | [Project Brief](https://pmdecoder.com/en/glossary/project-brief/) | partially overlapping | Preliminary form: basis for the decision on initiation; the project itself is authorized with the project initiation documentation. |
| cross-framework | Project outline | partially overlapping | preliminary form, usually without formal approval |
| Scrum | — | no counterpart | Scrum does not define a formal authorization of a project |
| Kanban | — | no counterpart | — |

## Classification

- Broader term: Project documentation
- Narrower terms: Approval decision

## Distinction

Not to be confused with the requirements specification, which describes the functional requirements but grants no authority. It must also be distinguished from the project management plan, which is only created after authorization.

## In practice

On a construction project, the executive board signs the project mandate before budget is released and staff are assigned. Authorization rarely fails because of the document itself, but because authority is not stated explicitly. Who may request resources and who may not later determines the pace of the project and its potential for conflict.

## Frequently asked questions

### Who prepares the project mandate?

Usually the sponsor, often together with the designated project manager.

### What is the difference between a project mandate and a project charter?

In substance, the two largely coincide. Project charter is the designation used in the PMBOK Guide.

### Does the project mandate have to be in writing?

The standard contains no requirement on form; it only defines the term. Because it describes the project mandate as a document, written form is the obvious choice. In practice, verbal authorizations exist, but they make any later clarification of responsibilities more difficult.

## Related terms

- Project objective
- [Work breakdown structure](https://pmdecoder.com/en/glossary/work-breakdown-structure/)
- [Stakeholder](https://pmdecoder.com/en/glossary/stakeholder/)
- [Project phase](https://pmdecoder.com/en/glossary/project-phase/)

## Change log

- 2026-09-28: Added typical contents, clarified the answer on written form.
- 2026-09-14: Corrected the reference; the 2018 document is a technical report (ISO/TR 21506:2018).
- 2026-09-12: Added distinction from the requirements specification.

---