# Project Mandate

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Managementprodukte
- Edition: PRINCE2 7
- Concept: [Formal authorization of a project](https://pmdecoder.com/en/concept/formally-authorizing-a-project/)
- Topic area: [Initiating](https://pmdecoder.com/en/area/initiating/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/project-mandate-prince2/

## Definition

In PRINCE2, the project mandate is what triggers a project. It comes from the commissioning body outside the project, such as corporate management, a programme or a customer, and contains the information available there at the time of the trigger: usually the reason, outline objectives, initial constraints and often a proposal for the executive. Its form and scope are open; it can be a detailed document or a short note. The project mandate starts the process starting up a project, in which the project brief is developed from it. The mandate authorizes the preparation, not the delivery of the project.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Project mandate](https://pmdecoder.com/en/glossary/project-mandate/) | false friend | In ISO 21506 “project mandate” is the binding authorization of a project; in PRINCE2 the project mandate is only the external trigger that starts preparation. |
| PMI / PMBOK Guide | [Project charter](https://pmdecoder.com/en/glossary/project-charter/) | false friend | In ISO 21506 “project mandate” is the binding authorization of a project; in PRINCE2 the project mandate is only the external trigger that starts preparation. |
| PM² | [Project Charter](https://pmdecoder.com/en/glossary/project-charter-pm2/) | false friend | In ISO 21506 “project mandate” is the binding authorization of a project; in PRINCE2 the project mandate is only the external trigger that starts preparation. |
| Six Sigma | [Six Sigma project charter](https://pmdecoder.com/en/glossary/six-sigma-project-charter/) | false friend | In ISO 21506 “project mandate” is the binding authorization of a project; in PRINCE2 the project mandate is only the external trigger that starts preparation. |
| cross-framework | Project outline | false friend | In ISO 21506 “project mandate” is the binding authorization of a project; in PRINCE2 the project mandate is only the external trigger that starts preparation. |
| Scrum | — | no counterpart | Scrum does not define a formal authorization of a project |
| Kanban | — | no counterpart | — |

## Distinction

In the English version of ISO 21506, “project mandate” is the term for the document that formally puts a project into effect. The PRINCE2 project mandate, by contrast, stands at the very beginning and does not yet authorize a project; that role is later taken by the project board when it approves the project initiation documentation. The PMI project charter is also more binding.

## In practice

The board of a health insurance fund decides to digitalize communication with its members further and sends the head of organizational development a two-page note with the objective, the desired start date and a cost range. This note is the project mandate. An executive is then appointed, a project manager assigned and the project brief developed within a few weeks.

## Frequently asked questions

### Does the project mandate have to be a formal document?

No. What matters is that an authorized body provides the trigger. Missing information is added while the project is being prepared.

### Is the project mandate a management product of the project?

It is created outside the project and handed over from there. The project does not change it but carries its content forward in the project brief.

## Related terms

- [Project Brief](https://pmdecoder.com/en/glossary/project-brief/)
- [Project mandate](https://pmdecoder.com/en/glossary/project-mandate/)
- [Project charter](https://pmdecoder.com/en/glossary/project-charter/)
- Project outline
- [Project initiation](https://pmdecoder.com/en/glossary/project-initiation/)
- [Starting up a project](https://pmdecoder.com/en/glossary/starting-up-a-project/)
- [Executive (PRINCE2)](https://pmdecoder.com/en/glossary/executive-prince2/)

---