# Project Manager (PRINCE2)

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Praktik Organisation
- Edition: PRINCE2 7
- Concept: [Person responsible for managing a project](https://pmdecoder.com/en/concept/person-responsible-for-managing-a-project/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/project-manager-prince2/

## Definition

The Project Manager in PRINCE2 runs the project day to day on behalf of the Project Board and within the limits it has set. The role is held by a single person. The Project Manager plans, allocates work packages, monitors progress, manages risks, issues and quality, and reports to the Project Board. The Project Manager is responsible for ensuring that the agreed products are delivered to the required quality, within time and cost, and with the benefits in mind. As long as tolerances are respected, the Project Manager acts independently; otherwise the matter is escalated. The role belongs to the managing level between direction and the teams.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Project manager](https://pmdecoder.com/en/glossary/project-manager/) | closely related | Manages within the Project Board’s tolerances but owns neither the business case nor the decision to continue. |
| PMI / PMBOK Guide | [Project manager](https://pmdecoder.com/en/glossary/project-manager-pmi/) | closely related | Manages within the Project Board’s tolerances but owns neither the business case nor the decision to continue. |
| PM² | [Project Manager](https://pmdecoder.com/en/glossary/project-manager-pm2/) | closely related | in PM², explicitly belongs to the Provider Side and reports to the Solution Provider |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

The project manager in ISO 21506 and in PMI publications has a similar mandate. In PRINCE2, however, the role is clearly separated from the Project Board: the Project Manager does not decide whether the project continues and does not own the business case but prepares these decisions. The Project Manager should not also be a member of the Project Board.

## In practice

A retail company is opening twelve new branches. The project manager plans the stages, allocates work packages to shopfitting, IT and human resources and produces a progress report every two weeks. When two sites cannot be finished on time because building permits are missing, she presents options to the Project Board instead of changing the order of openings on her own authority.

## Frequently asked questions

### Can the Project Manager also be Team Manager?

Yes. On small projects the Project Manager often leads the teams directly, so no separate team management role is filled.

### Who appoints the Project Manager?

Usually the Executive, in agreement with the commissioning organization. This happens during start-up, before initiation begins.

## Related terms

- [Project manager](https://pmdecoder.com/en/glossary/project-manager/)
- [Project manager](https://pmdecoder.com/en/glossary/project-manager-pmi/)
- [Project Manager](https://pmdecoder.com/en/glossary/project-manager-pm2/)
- [Project Board](https://pmdecoder.com/en/glossary/project-board/)
- [Controlling a stage](https://pmdecoder.com/en/glossary/controlling-a-stage/)
- [Team Manager](https://pmdecoder.com/en/glossary/team-manager/)
- [Organizing practice](https://pmdecoder.com/en/glossary/organizing-practice/)
- [Highlight Report](https://pmdecoder.com/en/glossary/highlight-report/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.