# Project management plan

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Comprehensive project management plan](https://pmdecoder.com/en/concept/comprehensive-project-management-plan/)
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Canonical version: https://pmdecoder.com/en/glossary/project-management-plan/

## Definition

In PMI usage, the project management plan is the document that sets out how a project is to be carried out, monitored, controlled and closed. It brings together the subsidiary plans, for example on managing scope, schedule, cost, quality, resources, communications, risk, procurement and stakeholders, and contains the approved baselines for scope, schedule and cost. It also sets out the change procedure and the chosen life cycle. The plan is elaborated progressively and, once approved, is changed only through change control. Its extent and level of detail depend on the size and nature of the project.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | [Project Plan](https://pmdecoder.com/en/glossary/project-plan-prince2/) | false friend | Despite the name, not the comprehensive plan: the PRINCE2 project plan is only one part of the project initiation documentation and covers products, stages, dates and costs at a high level. |
| cross-framework | [Project plan](https://pmdecoder.com/en/glossary/project-plan/) | false friend | The project management plan comprises all subsidiary plans, including scope, schedule, cost, quality, risk and communication. Anyone who says “Projektplan” in German almost always means just the schedule. In international projects, this confusion regularly leads to misunderstandings about the scope of delivery. |
| ISO 21506 | Project management plan | equivalent | — |
| ISO 21506 | [Project plan](https://pmdecoder.com/en/glossary/project-plan-iso/) | equivalent | — |
| PRINCE2 | [Project Initiation Documentation](https://pmdecoder.com/en/glossary/project-initiation-documentation/) | closely related | Collection of management products that also includes the business case; its approval authorizes the project. |
| PM² | [Project Handbook](https://pmdecoder.com/en/glossary/project-handbook/) | closely related | contains the management approach and management plans; work breakdown, effort, cost and schedule are in the project work plan |

## Classification

- Narrower terms: [Cost management plan](https://pmdecoder.com/en/glossary/cost-management-plan/), [Quality management plan](https://pmdecoder.com/en/glossary/quality-management-plan/), [Resource management plan](https://pmdecoder.com/en/glossary/resource-management-plan/), [Risk management plan](https://pmdecoder.com/en/glossary/risk-management-plan-pmi/)

## Distinction

The project management plan as defined in ISO 21506 denotes the same thing from a cross-framework perspective. In everyday language a project plan is often understood to be just the schedule; the project management plan is considerably broader. The project charter authorizes the project, while the project management plan sets out how it will be managed.

## In practice

For the relocation of a data centre, the project manager draws up a project management plan. It refers to a schedule with three moving weekends, a budget with a reserve, a communications plan for business units and customers, and a plan for managing risks. It also specifies that changes above 50,000 euros are decided by the steering committee. When one weekend has to be postponed, the change is approved and the plan is updated.

## Frequently asked questions

### Does the project management plan have to be a single document?

No. In larger projects it often consists of a main document that refers to separate subsidiary plans and baselines. What matters is that all parts are consistent and are approved and maintained together.

### How is the plan handled in adaptive projects?

It is usually leaner and describes the framework, roles and cadence rather than detailed content. The actual work is then defined continuously in backlogs and iteration plans.

## Related terms

- [Project plan](https://pmdecoder.com/en/glossary/project-plan-iso/)
- [Baseline](https://pmdecoder.com/en/glossary/baseline/)
- [Project charter](https://pmdecoder.com/en/glossary/project-charter/)
- [Performance measurement baseline](https://pmdecoder.com/en/glossary/performance-measurement-baseline-pmi/)
- [Risk management plan](https://pmdecoder.com/en/glossary/risk-management-plan-pmi/)
- [Project plan](https://pmdecoder.com/en/glossary/project-plan/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.