# Project management office

abbr. PMO

- Framework: [ISO 21506](https://pmdecoder.com/en/framework/iso-21506/)
- Reference: ISO 21506:2024, 3.66
- Edition: ISO 21506:2024
- Concept: [Project management support function](https://pmdecoder.com/en/concept/project-management-support-function/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/project-management-office/

## Definition

A project management office is a permanent function or unit, or one set up for a major undertaking, that supports project work across the organization. Depending on its remit, it provides templates and methods, trains project managers, collects status reports, maintains key figures and prepares decisions for portfolio management. In some organizations it also runs projects itself.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK Guide | [Project management office](https://pmdecoder.com/en/glossary/project-management-office-pmi/) | equivalent | — |
| PRINCE2 | [Project Support](https://pmdecoder.com/en/glossary/project-support/) | closely related | A role within a single project, not a permanent unit; a project office may fill it. |
| PM² | [Project Support Team](https://pmdecoder.com/en/glossary/project-support-team/) | partially overlapping | supports only one project with administration, reporting and documentation, without overarching responsibility for methods |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Broadly, there are three types: supportive, with templates and advice; controlling, with binding standards and reviews; and directive, with its own project responsibility. A project office in the narrower sense, by contrast, provides administrative support to a single project only. A programme management office performs comparable tasks for a programme made up of several related projects.

## In practice

A state authority sets up a project management office after it turns out that nobody knew how many IT projects were running at the same time. In the first year, the office records all undertakings in a list, introduces a standard one-page report and briefs the authority's management every quarter. Only then are method standards made binding, so that the office is not perceived as a mere control body.

## Frequently asked questions

### Who does a project management office report to?

Usually to executive management, a board member or the division responsible for the project portfolio. A high-level reporting line strengthens its influence.

### Why do project management offices fail?

Often because they demand forms without noticeably helping the projects. Value is created when reports lead to decisions and templates save work.

## Related terms

- [Portfolio management](https://pmdecoder.com/en/glossary/portfolio-management/)
- [Programme management](https://pmdecoder.com/en/glossary/programme-management/)
- [Project-oriented organization](https://pmdecoder.com/en/glossary/project-oriented-organization/)
- [Portfolio](https://pmdecoder.com/en/glossary/portfolio/)

---