# Project Initiation Documentation

abbr. PID

- Framework: [PRINCE2](https://pmdecoder.com/en/framework/prince2/)
- Reference: PRINCE2 7, Managementprodukte
- Edition: PRINCE2 7
- Concept: [Comprehensive project management plan](https://pmdecoder.com/en/concept/comprehensive-project-management-plan/)
- Topic area: [Planning and project structure](https://pmdecoder.com/en/area/planning-and-project-structure/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/project-initiation-documentation/

## Definition

In PRINCE2, the project initiation documentation (PID) is the set of management products produced during initiation that define what will be delivered in the project, why, when, by whom and how. It includes in particular the detailed business case, the project plan, the management approaches for areas such as quality, risk, issues and communication, the project management team structure with role descriptions, and the arrangements for tailoring PRINCE2 to the project. By approving it, the project board authorizes the project. It then serves as the reference basis and is updated at stage boundaries.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Project plan](https://pmdecoder.com/en/glossary/project-plan/) | false friend | The project management plan comprises all subsidiary plans, including scope, schedule, cost, quality, risk and communication. Anyone who says “Projektplan” in German almost always means just the schedule. In international projects, this confusion regularly leads to misunderstandings about the scope of delivery. |
| ISO 21506 | Project management plan | closely related | Collection of management products that also includes the business case; its approval authorizes the project. |
| ISO 21506 | [Project plan](https://pmdecoder.com/en/glossary/project-plan-iso/) | closely related | Collection of management products that also includes the business case; its approval authorizes the project. |
| PMI / PMBOK Guide | [Project management plan](https://pmdecoder.com/en/glossary/project-management-plan/) | closely related | Collection of management products that also includes the business case; its approval authorizes the project. |
| PM² | [Project Handbook](https://pmdecoder.com/en/glossary/project-handbook/) | closely related | contains the management approach and management plans; work breakdown, effort, cost and schedule are in the project work plan |

## Distinction

The PMI project management plan and the project management plan under ISO 21506 serve a similar purpose. However, the PID is not a single file but a collection, and with the business case it also contains the justification. The project plan is only one component of the PID. It is also close to the project handbook in PM².

## In practice

For merging two data centres, the project manager prepares the PID over six weeks. It consists of a wiki space with the business case, the project plan, four management approaches, an organization chart with role descriptions and a page on tailoring the method. The project board reviews the content in one meeting, requires a higher risk reserve and authorizes the project after the change.

## Frequently asked questions

### Does the PID have to be a single document?

No. It can consist of several documents, a wiki or a tool. What matters is that it is clear which content belongs to it and which version is valid.

### How does the PID relate to the project brief?

The project brief is the basis for the decision to start initiation. The PID builds on it and is the basis for the decision to deliver the project.

## Related terms

- [Project Brief](https://pmdecoder.com/en/glossary/project-brief/)
- [Project Plan](https://pmdecoder.com/en/glossary/project-plan-prince2/)
- [Business Case](https://pmdecoder.com/en/glossary/business-case-prince2/)
- Project management plan
- [Project management plan](https://pmdecoder.com/en/glossary/project-management-plan/)
- [Project Handbook](https://pmdecoder.com/en/glossary/project-handbook/)
- [Initiating a project](https://pmdecoder.com/en/glossary/initiating-a-project/)
- [Communication Management Approach](https://pmdecoder.com/en/glossary/communication-management-approach/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.