# Project-End Report

- Framework: [PM²](https://pmdecoder.com/en/framework/pm2/)
- Reference: PM²-Leitfaden 3.1, Abschnitt 8.2
- Edition: PM² Guide 3.1
- Concept: [Captured lessons from projects](https://pmdecoder.com/en/concept/captured-lessons-from-projects/)
- Topic area: [Closing](https://pmdecoder.com/en/area/closing/)
- Canonical version: https://pmdecoder.com/en/glossary/project-end-report/

## Definition

In PM², the Project-End Report is produced after the Project-End Review Meeting and brings together the project's experience. It describes good practices, lessons learned, difficulties encountered and how they were resolved, and it assesses the effectiveness of the project as well as the management of costs, schedule, scope, quality, risks, issues, changes, communication, staffing and stakeholders. Recommendations for the period after the project, for example on maintenance, enhancements or follow-up projects, are also included. The Project Manager writes it with support from the core team and quality assurance; it is meant to serve future projects as a knowledge base.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | [Lessons learned](https://pmdecoder.com/en/glossary/lessons-learned-iso/) | partially overlapping | contains lessons learned, but also reports on the performance and outcome of the project |
| PMI / PMBOK Guide | [Lessons learned](https://pmdecoder.com/en/glossary/lessons-learned/) | partially overlapping | contains lessons learned, but also reports on the performance and outcome of the project |
| PRINCE2 | [Learn from experience principle](https://pmdecoder.com/en/glossary/learn-from-experience-principle/) | partially overlapping | Principle of using lessons at the start, throughout and at the end, not the lessons themselves. |
| PRINCE2 | [Lessons Log](https://pmdecoder.com/en/glossary/lessons-log/) | partially overlapping | Log in which lessons are collected during the project. |
| PRINCE2 | [Lessons Report](https://pmdecoder.com/en/glossary/lessons-report/) | partially overlapping | contains lessons learned, but also reports on the performance and outcome of the project |
| PRINCE2 | [End Project Report](https://pmdecoder.com/en/glossary/end-project-report/) | partially overlapping | Mainly evaluates project performance; lessons can be summarized in it or attached as a Lessons Report. |
| Scrum | [Sprint Retrospective](https://pmdecoder.com/en/glossary/sprint-retrospective/) | partially overlapping | continually improves the way the team works instead of documenting lessons for other initiatives |

## Distinction

Lessons learned are one component; the report is broader and also assesses project performance. The Project Progress Report, by contrast, describes the status during the project, whereas the Project-End Report looks back on the project as a whole.

## In practice

The Project-End Report for a portal for election volunteers records that the budget was kept but the deadline was missed by four weeks because the interface to the population register became available later than planned. It recommends clarifying external interfaces bindingly as early as initiation in future and proposes an extension for postal voting volunteers as a follow-up project.

## Frequently asked questions

### Who contributes to the Project-End Report?

The Project Manager writes it but should involve the relevant stakeholders so that the assessment is complete and balanced.

### Is the report also prepared for cancelled projects?

Yes. It is precisely then that it pays to record why the project was not continued and what future projects can learn from it.

## Related terms

- [Closing Phase](https://pmdecoder.com/en/glossary/closing-phase-pm2/)
- [Lessons learned](https://pmdecoder.com/en/glossary/lessons-learned/)
- [Knowledge management](https://pmdecoder.com/en/glossary/knowledge-management/)
- [Project Manager](https://pmdecoder.com/en/glossary/project-manager-pm2/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.