# Project Core Team

abbr. PCT

- Framework: [PM²](https://pmdecoder.com/en/framework/pm2/)
- Reference: PM²-Leitfaden 3.1, Abschnitt 4.10
- Edition: PM² Guide 3.1
- Concept: [Team carrying out the project work](https://pmdecoder.com/en/concept/team-carrying-out-the-project-work/)
- Topic area: [Project organization](https://pmdecoder.com/en/area/project-organization/)
- Canonical version: https://pmdecoder.com/en/glossary/project-core-team/

## Definition

In PM², the Project Core Team (PCT) is made up of the specialists who create the deliverables. Its composition is decided by the Project Manager, depending on the size and nature of the project. The team helps plan the scope and activities, works on the basis of the Project Work Plan and the schedule, reports progress, lends a hand when difficulties arise and contributes its experience to the closing review. It can also include the project manager of an external contractor and a project assistant.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| cross-framework | [Project team](https://pmdecoder.com/en/glossary/project-team/) | closely related | provider side only; the requesting organization's team does not belong to it |
| Scrum | [Scrum Team](https://pmdecoder.com/en/glossary/scrum-team/) | partially overlapping | includes the Product Owner and Scrum Master and is oriented to a product and its Product Goal, not to a time-limited project |

## Distinction

The Project Core Team is only part of what PM² calls the project team: that includes all roles of the directing, managing and performing layers. The Business Implementation Group works on the customer side on implementation, and the Project Support Team provides cross-cutting services.

## In practice

For a web portal, the core team consists of a designer, two developers, an editor and a tester. The Project Manager adds an accessibility expert for three months. During the Planning Phase the team estimates the work packages itself, and it reviews progress together every Friday.

## Frequently asked questions

### When is the Project Core Team formed?

Usually before the Planning Kick-off Meeting, so that the team can contribute to scope, estimates and schedule.

### Can external service providers be part of the core team?

Yes. The work of their staff is then coordinated by the contractor's project manager in close cooperation with the Project Manager.

## Related terms

- [Project Manager](https://pmdecoder.com/en/glossary/project-manager-pm2/)
- [Project team](https://pmdecoder.com/en/glossary/project-team/)
- [Performing Layer](https://pmdecoder.com/en/glossary/performing-layer/)
- [Provider Side](https://pmdecoder.com/en/glossary/provider-side/)
- [Project Work Plan](https://pmdecoder.com/en/glossary/project-work-plan/)

---