# Project closure

also: Project close-out

- Framework: [cross-framework](https://pmdecoder.com/en/framework/general/)
- Concept: [Closing stage of a project](https://pmdecoder.com/en/concept/closing-stage-of-a-project/)
- Topic area: [Closing](https://pmdecoder.com/en/area/closing/)
- Author: Dennis Hain
- Canonical version: https://pmdecoder.com/en/glossary/project-closure/

## Definition

Project closure brings a project to an orderly end. It includes acceptance and handover of the results to users or operations, the final account, ending contracts, archiving the documentation, evaluating the experience gained and returning staff and resources to the line organization. A project that has been cancelled also needs a proper closure.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | [Closing a project](https://pmdecoder.com/en/glossary/closing-a-project/) | closely related | Process within the final stage rather than a stage of its own; also used for premature closure. |
| PM² | [Closing Phase](https://pmdecoder.com/en/glossary/closing-phase-pm2/) | closely related | fixed phase after the Ready for Closing phase gate, with the Project-End Report |
| Six Sigma | [Control phase](https://pmdecoder.com/en/glossary/control-phase/) | closely related | Closes the project, but focuses on securing the improvement for the long term and handing it over to the process owner. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |

## Distinction

Acceptance is part of closure, not the whole of it: remaining work, warranty periods and administrative tasks often follow. Lessons learned are the evaluation of content; project closure is the organizational framework for it. It differs from the closure of a phase in that no further stage of the project follows.

## In practice

After rolling out a new point-of-sale system in 120 branches, the team wants to move straight on to the next undertaking. The project manager insists on two weeks for closure: open items are passed to IT operations, service provider contracts are terminated, access rights deleted, and experience is gathered in a half-day workshop. Six months later the handover list proves valuable, because when a fault occurs, operations can trace which settings were chosen deliberately.

## Frequently asked questions

### Why is project closure often neglected?

Because the result is already in use, the team is under pressure from new tasks and the closure itself promises no visible benefit.

### What belongs in a closure report?

Achievement of objectives, a summary of schedule and cost performance, open items with the people responsible, key experience and recommendations for follow-on projects.

## Related terms

- [Lessons learned](https://pmdecoder.com/en/glossary/lessons-learned/)
- [Formal acceptance](https://pmdecoder.com/en/glossary/formal-acceptance/)
- [Project life cycle](https://pmdecoder.com/en/glossary/project-life-cycle/)
- [Historical data](https://pmdecoder.com/en/glossary/historical-data/)

---