# Project charter

- Framework: [PMI / PMBOK Guide](https://pmdecoder.com/en/framework/pmi-pmbok/)
- Reference: PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition: PMBOK Guide – Eighth Edition
- Concept: [Formal authorization of a project](https://pmdecoder.com/en/concept/formally-authorizing-a-project/)
- Topic area: [Initiating](https://pmdecoder.com/en/area/initiating/)
- Canonical version: https://pmdecoder.com/en/glossary/project-charter/

## Definition

In PMI usage, the project charter is the document with which a project officially begins. It is issued by someone outside the project, normally the sponsor. It determines who will lead the project and how far that person’s authority extends, particularly over staff, money and other means belonging to the organization. It also records briefly why the project is being carried out, what it is meant to achieve and within which limits it operates. The charter is deliberately short and changes little over the life of the project; the details of planning follow in the project management plan.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | [Project Mandate](https://pmdecoder.com/en/glossary/project-mandate-prince2/) | false friend | In ISO 21506 “project mandate” is the binding authorization of a project; in PRINCE2 the project mandate is only the external trigger that starts preparation. |
| ISO 21506 | [Project mandate](https://pmdecoder.com/en/glossary/project-mandate/) | equivalent | — |
| PM² | [Project Charter](https://pmdecoder.com/en/glossary/project-charter-pm2/) | closely related | forms the basis for approval together with the business case; the project manager has already been appointed |
| Six Sigma | [Six Sigma project charter](https://pmdecoder.com/en/glossary/six-sigma-project-charter/) | closely related | Tailored to an improvement project with a measurable output, usually shorter and still updated during the first phases. |
| PRINCE2 | [Project Brief](https://pmdecoder.com/en/glossary/project-brief/) | partially overlapping | Preliminary form: basis for the decision on initiation; the project itself is authorized with the project initiation documentation. |
| cross-framework | Project outline | partially overlapping | preliminary form, usually without formal approval |
| Scrum | — | no counterpart | Scrum does not define a formal authorization of a project |
| Kanban | — | no counterpart | — |

## Distinction

The project mandate under ISO 21506 largely corresponds to the project charter. The PM² Project Charter builds on a business case that has already been prepared, and the project manager has been named by then. The PRINCE2 Project Mandate, by contrast, is merely the trigger that starts the preparation of a project. The business case explains why a project is worthwhile and the project management plan describes how it will be carried out; the charter puts the project into effect and assigns authority.

## In practice

A logistics company is switching its warehouses to a new scanning system. The responsible board member, acting as sponsor, signs a two-page project charter: the picking error rate is to be halved within a year, and the budget ceiling is 1.2 million euros. An IT employee is named project manager and may request staff from three sites and award contracts of up to 50,000 euros on his own. When one site manager refuses to release his people, the project manager points to this provision and the conflict is quickly resolved.

## Frequently asked questions

### Who approves the project charter?

It is approved by a person or body outside the project that has the necessary authority and resources, usually the sponsor. The future project manager often helps to draft it.

### What does a project charter contain?

Typical contents are the purpose and justification of the project, measurable objectives, high-level requirements, key milestones, a budget range, major risks and stakeholders, and the appointment of the project manager with their authority.

### How does the project charter differ from the German Projektauftrag?

In substance the two largely coincide. The project charter explicitly covers appointing the project manager and their authority to use organizational resources.

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.
