# Project Charter

- Framework: [PM²](https://pmdecoder.com/en/framework/pm2/)
- Reference: PM²-Leitfaden 3.1, Abschnitt 5.4
- Edition: PM² Guide 3.1
- Concept: [Formal authorization of a project](https://pmdecoder.com/en/concept/formally-authorizing-a-project/)
- Topic area: [Initiating](https://pmdecoder.com/en/area/initiating/)
- Canonical version: https://pmdecoder.com/en/glossary/project-charter-pm2/

## Definition

In PM², the Project Charter provides the basis for more detailed planning. It describes what the project is to achieve in terms of scope, time, cost and quality, which high-level requirements, risks and constraints apply, and which milestones and deliverables are planned. It thus records what is to be delivered, how and by when, and later serves as the yardstick for measuring progress. Together with the Business Case, it is the central document for project approval. The Business Manager can initiate it, but the Project Manager is responsible for finalizing it and presenting it for approval. It should remain short and be updated when necessary.

## Equivalents in other frameworks

| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | [Project Mandate](https://pmdecoder.com/en/glossary/project-mandate-prince2/) | false friend | In ISO 21506 “project mandate” is the binding authorization of a project; in PRINCE2 the project mandate is only the external trigger that starts preparation. |
| ISO 21506 | [Project mandate](https://pmdecoder.com/en/glossary/project-mandate/) | closely related | forms the basis for approval together with the business case; the project manager has already been appointed |
| PMI / PMBOK Guide | [Project charter](https://pmdecoder.com/en/glossary/project-charter/) | closely related | forms the basis for approval together with the business case; the project manager has already been appointed |
| Six Sigma | [Six Sigma project charter](https://pmdecoder.com/en/glossary/six-sigma-project-charter/) | closely related | Tailored to an improvement project with a measurable output, usually shorter and still updated during the first phases. |
| PRINCE2 | [Project Brief](https://pmdecoder.com/en/glossary/project-brief/) | partially overlapping | Preliminary form: basis for the decision on initiation; the project itself is authorized with the project initiation documentation. |
| cross-framework | Project outline | partially overlapping | preliminary form, usually without formal approval |
| Scrum | — | no counterpart | Scrum does not define a formal authorization of a project |
| Kanban | — | no counterpart | — |

## Distinction

The English name Project Charter matches the PMI term of the same name. Unlike the project charter under ISO 21506, the PM² Project Charter does not itself appoint the Project Manager; the Solution Provider has already done so beforehand. Detailed requirements belong in separate documents or an annex.

## In practice

For the electronic delivery of notices, the Project Charter sets out on six pages: delivery via the existing citizen account, a start in two pilot units by June, a budget of 180,000 euros and the risk of a low take-up rate. The Project Steering Committee accepts it, and the Project Owner submits it together with the Business Case to the responsible governance body.

## Frequently asked questions

### What distinguishes the Project Charter from the Business Case in PM²?

The Business Case justifies why the project is worthwhile and sets the budget framework. Building on it, the Project Charter describes exactly what will be delivered, with which milestones and under which constraints.

### Who approves the Project Charter?

The Project Steering Committee accepts it; depending on the organization, the Appropriate Governance Body also approves it.

## Related terms

- [Project Initiation Request](https://pmdecoder.com/en/glossary/project-initiation-request/)
- [Business case](https://pmdecoder.com/en/glossary/business-case/)
- [Ready for Planning](https://pmdecoder.com/en/glossary/ready-for-planning/)
- [Project Work Plan](https://pmdecoder.com/en/glossary/project-work-plan/)
- [Project mandate](https://pmdecoder.com/en/glossary/project-mandate/)

---

Independent information service. Not published, reviewed or authorized by ISO, PMI or the publishers of the other frameworks. The original text is authoritative in each case.